A cost-benefit analysis puts a decision’s costs and benefits side by side, year by year, against the alternative of carrying on as you are, converts both into today’s money and tells you whether the change pays. This free template does the arithmetic in Excel: cost and benefit registers, net present value (NPV), payback, return on investment (ROI), the benefit-cost ratio and a sensitivity tab that finds the one assumption that would change your answer.
Free, UK English, no sign-up. Blank registers plus a fully worked example: a 22-person IT firm deciding whether to replace its office server or move to the cloud.
Key takeaways
- Compare against business as usual, never against zero. Carrying on usually costs money too: the old server still has to be replaced.
- Grade every benefit: cash (a bill changes), capacity (time freed, cash only if used or sold) or comfort (real, but no bill changes). Decide on cash first.
- Discount at your own price of money, such as your loan rate. A pound next year is worth less than a pound today because you could have used it in between.
- Read NPV first. Payback, ROI and the benefit-cost ratio describe the result; they do not decide it.
- Find the switching value: the change in one assumption that turns the answer from yes to no. In our example a subscription rise of about 9% is enough.
- In Excel, keep year 0 outside NPV():
=B5+NPV(8%,C5:G5).
What is a cost-benefit analysis?
A cost-benefit analysis (CBA) prices the effects of a decision in money, over the years they occur, and compares the total with what would happen otherwise. It is the method HM Treasury’s Green Book recommends for comparing a shortlist of options in detail, and it scales down well: the same logic serves a council weighing a bypass and a small firm weighing a new server.
The mechanism is simple once you see it. Every decision changes some money flows: it adds costs, removes others, and brings in new income. Write those changes down by year, and two questions remain. Do the gains outweigh the costs? And does the timing matter? It does, because a pound you spend today is a pound you cannot use for anything else in the meantime. Discounting is the correction for that, and the net present value is the result.
A cost-benefit analysis is the numbers, not the whole decision. The business case template is the document that carries them, with the problem, the options, the risks and the recommendation; this page is the engine room underneath it. If you are working out what a customer is worth over their lifetime rather than whether a project pays, our unit economics guide is the better tool.
How to do a cost-benefit analysis in six steps
- Name the decision and the alternative. Write one sentence: what you would do, by when, compared with what. The comparison is business as usual, and business as usual is rarely free: the old server still needs replacing, the old process still needs staff.
- Register every cost, year by year. One-off costs in year 0, running costs in the years they fall. Include your own people's time, and mark it as capacity, not cash.
- Register the benefits and grade them. Every benefit is cash, capacity or comfort. Costs you avoid by not doing business as usual are benefits of the proposal.
- Discount at your own price of money. Turn each year's figures into today's money with the rate you pay to borrow, or the return you could get elsewhere, then add them up: that is the net present value (NPV).
- Read four numbers, in this order. NPV first, then payback, return on investment (ROI) and the benefit-cost ratio (BCR). Read the cash-only figures before the ones that include capacity.
- Try to break it. Change each big assumption, find the value at which the answer flips (the switching value), and add an allowance for optimism. If a plausible change flips the decision, say so.
Two of these steps do most of the work. The first, because the comparison decides everything: the Green Book’s own warning is that business as usual “does not mean doing nothing”, and a proposal judged against an imaginary zero always looks better than it is. The last, because a single NPV is a point estimate built on guesses, and the useful question is not “what is the answer?” but “how wrong would I have to be for the answer to change?”.
Cash, capacity or comfort: grading the benefits
The fastest way to make a cost-benefit analysis honest is to sort every benefit by what actually changes in the bank. The benefits column is where an analysis is easiest to inflate: add up hours saved, risks reduced and morale improved as if each were money arriving, and almost anything pays.
| Grade | What counts | How to treat it |
|---|---|---|
| Cash | A bill stops, a bill shrinks, or money starts arriving. You could point to the bank statement where it shows. | Count it in full. This is the number the decision should stand on. |
| Capacity | Time or effort freed: hours no longer spent on a task. It turns into cash only if a bill changes (overtime, a contractor, a hire you no longer need) or the time is sold. | Price it at cost, show it on its own line, and name who will use the freed time and on what. |
| Comfort | Lower risk, better service, happier staff, resilience. Real, but no bill changes. | Describe it, say how you would notice it, and do not add it to the totals. Where you can, price a risk as an expected loss and show it separately. |
Apply the same rule to costs. If your own staff spend twelve days on a project, that is capacity used, not cash spent, unless you pay overtime or bring in cover. Treating staff time one way on the cost side and another on the benefit side is an easy way to tilt an analysis without noticing.
Capacity is not worthless. It is conditional. Ten hours a week freed in a team that is already stretched may be worth more than the cash line, because it is what lets the business take on work it is turning away. But that only happens if someone decides it will, so the template asks you to name who uses the freed time, and on what. A benefit with no owner is a hope.
An hour saved is only money if a bill changes or someone sells the hour.
Comfort benefits, such as lower risk, better service or happier staff, stay out of the totals. Describe each one, say how you would notice it (fewer remote-access tickets, a monthly restore test that passes) and give it an owner. Where a risk can be priced, price it as an expected loss (the chance it happens in a year multiplied by what it would cost) and show it on its own line, so the reader can see how much of the case rests on it.
The formulas, worked by hand
Every number in a cost-benefit analysis comes from one idea: money now is worth more than the same money later, by your discount rate for each year you wait. At 8% a year, £1,000 in a year’s time is worth £1,000 ÷ 1.08 = £926 today, and £1,000 in three years is worth £1,000 ÷ 1.08³ = £794. The multipliers (1, 0.926, 0.857, 0.794 and so on) are discount factors.
Take a simple proposal: spend £10,000 now to save £3,000 a year for five years, at 8%.
| Year | Saving | Discount factor at 8% | Present value | Cumulative cash | Cumulative discounted |
|---|---|---|---|---|---|
| Year 0 | -£10,000 | 1.000 | -£10,000 | -£10,000 | -£10,000 |
| Year 1 | £3,000 | 0.926 | £2,778 | -£7,000 | -£7,222 |
| Year 2 | £3,000 | 0.857 | £2,572 | -£4,000 | -£4,650 |
| Year 3 | £3,000 | 0.794 | £2,381 | -£1,000 | -£2,269 |
| Year 4 | £3,000 | 0.735 | £2,205 | £2,000 | -£64 |
| Year 5 | £3,000 | 0.681 | £2,042 | £5,000 | £1,978 |
- Present value (PV) = amount ÷ (1 + rate)year. The fourth column.
- Net present value (NPV) = present value of benefits minus present value of costs = £11,978 − £10,000 = £1,978. Above zero, so the saving beats leaving the money where it is, at 8%.
- Payback = the point where cumulative cash turns positive: after year 3 you are £1,000 short, and year 4 brings £3,000, so payback is 3 + 1,000 ÷ 3,000 = 3.3 years.
- Discounted payback does the same with the discounted column: 4.0 years. At any discount rate above zero it is longer, because later money counts for less.
- Return on investment (ROI), over the whole period and not discounted = (£15,000 − £10,000) ÷ £10,000 = 50%. Easy to quote, and easy to flatter, because it treats year-five money as if it arrived today.
- Benefit-cost ratio (BCR) = present value of benefits ÷ present value of costs = £11,978 ÷ £10,000 = 1.20. Above 1.0 is the same statement as a positive NPV.
Payback has two blind spots: it ignores everything after the payback date, and plain payback ignores timing altogether. It answers “how long is our money at risk?”, which is a fair question, but not “is this worth doing?”. That is NPV’s job.
The Excel NPV trap
Excel’s NPV function assumes the first value you give it arrives one period from now. Microsoft’s own documentation says a cash flow at the start of the first period must be added to the result, not included in the range. So if your year 0 outlay is in B5 and years 1 to 5 are in C5 to G5, the right formula is =B5+NPV(8%,C5:G5). Writing =NPV(8%,B5:G5) discounts the money you spend today as if it left a year from now, and on the example above it turns £1,978 into £1,832. It is an easy slip, and it appears in some of the AI-written answers to this very question. The results tab in our workbook calculates NPV both ways so you can see they agree.
Cost-benefit analysis example: replace the server or move to the cloud?
Harbour Lane IT Ltd, a 22-person managed IT services firm (fictional), has an office server that runs its file shares and its accounts and practice-management software, and the server’s operating system is about to go out of support. The obvious move is to buy a new one. The alternative is to move the files to cloud storage and the accounts software to its supplier’s hosted version, and retire the server. Harbour Lane is the same firm that runs through our gap analysis and profit and loss examples.
The decision, in one sentence each
Proposal: Move the office file shares and the accounts and practice-management software off the office server and onto cloud services, instead of replacing the server, before its operating system goes out of support.
Business as usual: Buy a replacement server with new operating-system and user licences, have an engineer build it and move the data across, and keep running it, its backups and its support contracts for five years.
Settings: five years, to match the life of a new server; today’s prices; a discount rate of 8%, the interest rate on the firm’s bank loan. Staff time at a loaded day rate of £183 (a £36,000 salary plus employer National Insurance and pension, over 232 working days).
Every row in the register is a difference from business as usual. The costs of moving are the migration and the subscriptions. The benefits include the costs Harbour Lane avoids by not replacing the server: the hardware, the licences, the support contracts, the electricity and the engineer time spent looking after it.
| ID | Type | Line and basis | Year 0 | Year 1 | 5-year total |
|---|---|---|---|---|---|
| C1 | Cost Cash | Specialist to move the accounts database to the hosted service Supplier's fixed quote | £1,800 | £1,800 | |
| C2 | Cost Capacity | Engineer time: plan, move and test files and permissions 12 days × £183 loaded day rate | £2,196 | £2,196 | |
| C3 | Cost Capacity | Staff time: learning the new file locations 22 staff × 2 hours, at £183 a day | £1,074 | £1,074 | |
| C4 | Cost Cash | Licence upgrade for cloud file storage and device management £5 a user a month × 22 users | £1,320 | £6,600 | |
| C5 | Cost Cash | Hosted accounts and practice-management software Supplier's quote, £200 a month | £2,400 | £12,000 | |
| C6 | Cost Cash | Backup of the cloud files and mailboxes £2.50 a user a month × 22 users | £660 | £3,300 | |
| C7 | Cost Capacity | Engineer time: looking after the cloud set-up 4 days a year × £183 | £732 | £3,660 | |
| B1 | Benefit Cash | Replacement server not bought Hardware quote, with three-year warranty | £6,500 | £6,500 | |
| B2 | Benefit Cash | Server operating system and user licences not bought Licence quote | £2,600 | £2,600 | |
| B3 | Benefit Capacity | Engineer time to build the replacement server avoided 6 days × £183 | £1,098 | £1,098 | |
| B4 | Benefit Cash | On-site accounts software support contract ends Current annual contract | £1,250 | £6,250 | |
| B5 | Benefit Cash | Server hardware support not needed in years 4 and 5 Extended warranty quote, £480 a year | £960 | ||
| B6 | Benefit Cash | Electricity for the server, storage and uninterruptible power supply (UPS) Firm's own estimate | £700 | £3,500 | |
| B7 | Benefit Cash | On-site backup storage and off-site copy service end Current contracts | £720 | £3,600 | |
| B8 | Benefit Capacity | Engineer time on patching, backup checks and server faults avoided 18 days a year × £183, from the ticket log | £3,294 | £16,470 | |
| B9 | Benefit Cash | UPS batteries and a disk replacement avoided Expected in year 3 | £450 |
Now the result, cash first.
| Cash only | Year 0 | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 |
|---|---|---|---|---|---|---|
| Benefits | £9,100 | £2,670 | £2,670 | £3,120 | £3,150 | £3,150 |
| Costs | £1,800 | £4,380 | £4,380 | £4,380 | £4,380 | £4,380 |
| Net | £7,300 | -£1,710 | -£1,710 | -£1,260 | -£1,230 | -£1,230 |
| Cumulative | £7,300 | £5,590 | £3,880 | £2,620 | £1,390 | £160 |
| Discount factor at 8% | 1.000 | 0.926 | 0.857 | 0.794 | 0.735 | 0.681 |
| Discounted net | £7,300 | -£1,583 | -£1,466 | -£1,000 | -£904 | -£837 |
This is the shape that makes server-versus-cloud decisions confusing. In a typical project you spend first and earn later, so payback is a sensible question. Here the money flows the other way: Harbour Lane saves £7,300 up front by not buying the server, then pays it back, in effect, as subscriptions that cost £1,710 a year more than the running costs they replace. There is nothing to pay back, so payback is meaningless, and a higher discount rate makes the cloud look better, not worse, because it shrinks costs that arrive later.
| At 8% over five years | Cash only | Cash and capacity |
|---|---|---|
| Net present value (NPV) | £1,509 | £9,567 |
| Payback | None: benefits come first | None: benefits come first |
| Return on investment (ROI), five years | 0.7% | 35.3% |
| Benefit-cost ratio (BCR) | 1.08 | 1.38 |
On cash alone the move is marginally better: an NPV of £1,509, a benefit-cost ratio of 1.08 and, over five undiscounted years, a gain of only £160. The stronger case is capacity. The firm stops spending 18 engineer days a year on patching, backup checks and server faults and starts spending 4 on the cloud set-up, freeing 14 days a year. Valued at cost, that lifts the NPV to £9,567, but only if the days go somewhere useful. Harbour Lane’s answer is to put them into the packaged Cyber Essentials certification service the gap analysis found it did not yet offer, with the service desk lead as owner.
What the numbers leave out
Four benefits stay out of the totals, each with a way of noticing it and an owner:
| Comfort benefit (not priced) | How Harbour Lane will notice it | Owner |
|---|---|---|
| Staff reach files from home or a client site without the virtual private network (VPN) | Remote-access tickets per month | Operations manager |
| No single box in the comms cupboard that stops the office when it fails | Hours of office-wide downtime a year | Service desk lead |
| Off-site copies of files and mail by default | Monthly restore test passes | Service desk lead |
| The firm runs on the services it sells, which helps when it advises clients | Cloud projects won where this came up | Managing director |
And the costs no register catches:
- A broadband failure stops access to files. Keep a 4G backup line and sync the most-used folders to laptops.
- Subscription prices can rise every year. Fix prices for three years in the contract, or carry a price-rise allowance.
- Data now sits with a supplier. Check the service against the National Cyber Security Centre's (NCSC) cloud security principles before signing.
The security point deserves a sentence of its own. Moving data to a supplier changes who protects it, so check the service before signing: the NCSC’s guidance on choosing a cloud provider offers a lightweight approach for smaller organisations and warns that a certificate on its own is not enough. If the files are moving to SharePoint or Google Drive, our shared drive folder structure guide covers how to lay them out.
Sensitivity analysis: what would change the answer?
Sensitivity analysis changes one assumption at a time and watches the result; a switching value is the change that turns a yes into a no. HM Treasury defines switching values as “the values that a key assumption would need to change to, in order to make an option no longer value for money”, which is the question a decision-maker actually needs answered.
There is a neat shortcut. NPV is a sum, so if a group of costs rises by 10%, NPV falls by 10% of that group’s present value, no more, no less. The switching value is therefore one division: the NPV divided by the group’s effect on NPV. The sensitivity tab does this for every group you name.
| Group | Cash NPV, group 20% lower | Cash NPV, group 20% higher | Switching value, cash | Switching value, with capacity |
|---|---|---|---|---|
| Subscriptions (C4 to C6) | £5,007 | -£1,988 | +9% | +55% |
| Running savings (B4 to B7, B9) | -£830 | £3,849 | -13% | -82% |
| Avoided server (B1, B2) | -£311 | £3,329 | -17% | -105% |
| Migration, cash (C1) | £1,869 | £1,149 | +84% | +189% |
Read it from the top. The cash case survives a much dearer migration (it would take an 84% overrun to sink it), but it fails if the subscriptions cost about 9% more than quoted, or if the running savings come in 13% lower. Suppliers set subscription prices at each renewal, so a rise of that size over five years cannot be ruled out, and the honest conclusion is that the cash case is fragile. With capacity counted, the subscriptions would have to rise by 55% to sink it.
Then add an allowance for optimism. The Green Book describes optimism bias as “the proven tendency for appraisals to be over-optimistic about key assumptions” and asks appraisers to raise cost estimates and lower benefit estimates to correct for it. With an illustrative allowance of one-off costs up 50% and every benefit down 20%, Harbour Lane’s cash NPV becomes -£3,550, and the cash-and-capacity NPV falls to about £22: break-even.
Harbour Lane’s recommendation
Go, on two conditions. First, fix the subscription prices for three years in the contracts, because a rise of about 9% removes the cash case. Second, give the 14 freed engineer days a year an owner and a job (the Cyber Essentials service), because without them the move is close to break-even. Review the register against actual figures at month 12, and record the decision in the decision log.
What discount rate should a small business use?
Use your own price of money: the interest rate you pay to borrow, or, if you are spending cash you already have, the return you would give up by not putting it elsewhere. The discount rate is not a measure of risk or a fudge factor. It answers one question: what does it cost this business to have money tied up for a year?
For a firm funding the project from a loan or overdraft, that is the interest rate. For a firm with cash on deposit and nothing better to do with it, it might be the deposit rate, which is lower. A firm that turns away profitable work for lack of cash should use a higher rate, because money spent here is money not spent there. If you cannot decide, test a range. Harbour Lane’s cash NPV across the range:
| Discount rate | 0% | 3% | 5% | 8% | 10% | 12% | 15% |
|---|---|---|---|---|---|---|---|
| Cash NPV | £160 | £721 | £1,056 | £1,509 | £1,782 | £2,034 | £2,377 |
Two points about the public-sector rate. HM Treasury’s Green Book rate is a social time preference rate, “the rate at which society is willing to trade off consumption today for consumption tomorrow”, set for spending public money. A business should use the rate it actually faces; if that is higher, borrowing the public rate makes long projects look better than they are. And whatever rate you choose, match it to your prices. The Green Book removes general inflation before discounting, and our template is built the same way, in today’s prices. Strictly, a loan rate includes expected inflation, so with today’s prices you would take inflation off it to get a real rate. For Harbour Lane it makes no difference to the verdict, because the cash NPV is positive at every rate in the table, but it matters more as the period lengthens. What you must not do is mix the two: prices that include inflation with a rate that excludes it, or the reverse.
Where cost-benefit analyses go wrong
- The wrong comparison. Comparing with doing nothing, when doing nothing is not on offer. If the server must be replaced anyway, its cost belongs in business as usual.
- Soft benefits counted as cash. Hours saved, risks avoided and morale improved are graded, not added. The capacity column exists so they can be shown honestly rather than left out or smuggled in.
- Optimism. Costs come in higher, benefits lower and both later than planned. Show an allowance, or use your own record of past projects to set one.
- Double counting. The same saving claimed twice, once as fewer support tickets and again as engineer time, or claimed by two projects at once. One benefit, one row, one owner.
- Benefits that grow to fit the decision. Add enough years and enough benefits and anything can be justified. Match the period to the life of the thing you are buying, and list only benefits you can explain the cause of.
- Sunk costs. Money already spent, such as a feasibility study or last year’s hardware, is the same whichever way you decide, so it stays out.
- Mismatched lives. Comparing a five-year subscription with a server that would last seven ignores the two years of value left in the server. Either match the periods or add a residual value.
- Inflation and discounting mixed up. Today’s prices with a real rate, or inflated prices with a nominal rate. Never one of each.
- Payback used as the verdict. It says how long money is at risk, not whether the project pays, and it says nothing at all when the savings come first.
Do you need a full cost-benefit analysis?
Match the effort to the money and the uncertainty. For a purchase you could reverse next month, the back of an envelope will do: one line of costs, one of savings, and the payback. For anything that commits money for more than a year, or that you would struggle to undo, use the workbook: an hour with the registers is cheap insurance. For a decision that will be scrutinised by a lender, a grant funder or a public body, expect to be asked for the full apparatus, in the format they set; the Green Book is the reference for public money.
The free route goes a long way. The workbook is built for Excel and uses only functions that LibreOffice and Google Sheets also support, and the method needs no software at all. If you need to choose between several proposals rather than test one, score them first with the project prioritisation scorecard, then run a cost-benefit analysis on the front runners. The risks you uncover belong in a risk register.
Books worth reading before you decide
The workbook does the arithmetic. These three books help with the parts it cannot do for you: writing the case, putting a value on benefits that look unmeasurable, and making sure the benefits you counted turn up. Every link goes to Amazon UK and is an affiliate link: as an Amazon Associate, IT Management 101 earns from qualifying purchases, at no extra cost to you.

HBR Guide to Building Your Business Case
Raymond Sheen, with Amy Gallo
A short, practical guide to the step after this page: turning a register and an NPV into a case that someone senior can approve, with the costs, benefits and risks set out in the order they will ask about them.

How to Measure Anything: Finding the Value of Intangibles in Business
Douglas W. Hubbard
For the capacity and comfort columns. Its argument is that a benefit you cannot measure exactly can still be measured well enough to reduce your uncertainty, and that an honest range beats a confident single figure.

Benefit Realisation Management (2nd edition)
Gerald Bradley
The analysis predicts benefits; this book is about making them arrive. It is written for larger change programmes, but the core habit scales down: give every benefit an owner and measure it after go-live, so your next set of estimates is better than this one.
Disclosure: as an Amazon Associate, IT Management 101 earns from qualifying purchases. If you buy through these links we may receive a small commission, at no extra cost to you. Availability and links were checked on 15 November 2026 and can change. Harvard Business Review is not connected with this page.
UK figures to check (checked 15 November 2026; review by 15 November 2027)
- Public-sector discount rate: HM Treasury cut the Green Book discount rate for years 1 to 30 from 3.50% to 3.00% a year in October 2026 (HM Treasury response). It is for public-sector appraisal; a business discounts at its own cost of money.
- Tax on a server you buy: a purchased server can usually qualify for capital allowances such as the Annual Investment Allowance, which covers most plant and machinery up to £1 million a year (GOV.UK), while a subscription is a running cost. The two get tax relief at different times. Our template works before tax; ask your accountant how the timing affects your figures.
- Server support dates: Microsoft’s lifecycle page lists extended support for Windows Server 2016 as ending in January 2027 (Microsoft Lifecycle). Check your own server’s version on the same site before you build a case around it.
Download the free cost-benefit analysis template
Cost-benefit analysis template: Excel, Word and PDF
Excel: a cost and benefit register for up to 40 lines over year 0 to year 7, with Cost/Benefit and Cash/Capacity drop-downs; a results tab with NPV, payback, discounted payback, ROI and the benefit-cost ratio for cash alone and with capacity, plus the Excel NPV check; a sensitivity tab with switching values for each group you name, a discount-rate table and an optimism allowance; and a comfort tab for unpriced benefits, dis-benefits and freed capacity. The Harbour Lane example runs on the same live formulas. Word and PDF: a one-page summary for the person who decides (blank and filled in), the example register and cash table, and a page on method and formulas.
Licensed under Creative Commons Attribution-NonCommercial 4.0 (CC BY-NC 4.0): use and adapt it freely in your own business, teaching or training. If you share it, please link to this page.
Using a cost-benefit analysis to support a proposal? The project proposal template and the business case template are the documents it usually goes into.
Frequently asked questions
What is a cost-benefit analysis template?
A ready-made spreadsheet that lists what a decision will cost and what it will bring in, year by year, against the alternative of carrying on as you are, and turns the two into today's money so you can compare them. Ours, in Excel, also works out net present value (NPV), payback, return on investment (ROI) and the benefit-cost ratio, and has a sensitivity tab that finds the assumption that would change the answer.
What should a cost-benefit analysis include?
One sentence saying what you would do and what you are comparing it with; every cost and benefit by year, with the basis of each figure; your discount rate; the results (NPV first, then payback, ROI and the benefit-cost ratio); a sensitivity test showing which assumption would flip the answer; the benefits you cannot price, each with an owner; and a recommendation with any conditions attached.
What are the steps of a cost-benefit analysis?
Name the decision and the alternative; register every cost by year; register the benefits and grade each one as cash, capacity or comfort; discount everything to today's money; read NPV, payback, ROI and the benefit-cost ratio, cash-only figures first; then try to break the result by changing each big assumption.
How do you calculate NPV in Excel?
Put the year 0 figure outside the function and the later years inside it: =B5+NPV(8%,C5:G5), where B5 is year 0 and C5 to G5 are years 1 to 5. Excel's NPV function treats its first value as one period away, so including year 0 in the range pushes every figure a year later and divides the true answer by one plus the rate: in our simple example, £1,832 instead of £1,978.
What is a good benefit-cost ratio?
Anything above 1.0 means the discounted benefits exceed the discounted costs, which is the same as a positive NPV. How far above 1.0 you need depends on how sure you are of the figures: a ratio of 1.08, as in our example, can be wiped out by a modest change in one assumption, so look at the switching values before you take comfort from it.
What is the difference between a cost-benefit analysis and a business case?
The cost-benefit analysis is the numbers: costs, benefits, discounting and the sensitivity test. The business case is the decision document that carries them, with the problem, the options, risks, timescale and the recommendation. Most business cases contain a cost-benefit analysis; our business case template has the rest of the document.
Should staff time count as a benefit?
Count it, but on its own line. Hours saved become money only if a bill changes, such as less overtime, a contractor you stop paying or a hire you no longer need, or if the time is sold. So price freed time at cost as capacity, show the result with and without it, and name who will use the time and on what. Treat staff time spent on the project the same way.
What discount rate should a small business use?
Your own price of money: the interest rate you pay to borrow, or the return you would give up by spending the cash, whichever applies. The HM Treasury rate in the Green Book is a social rate set for public money, not a business's cost of borrowing. If you are unsure, test a range: the sensitivity tab shows NPV from 0% to 15%.
Is cost-benefit analysis the same as ROI?
No. ROI is one number, usually the net gain as a share of cost, and it ignores when the money arrives. A cost-benefit analysis is the whole comparison, by year and discounted, with ROI as one of its outputs. Decide on NPV and use ROI as a quick way to describe the result.
Does the template work in Google Sheets?
It uses only standard functions (SUMIFS, SUMPRODUCT, NPV, IF and COUNT), drop-down lists and conditional formatting, all of which Google Sheets supports, and has no macros. We checked every formula by recalculating the file in LibreOffice. To use it in Google Sheets, upload the .xlsx file to Google Drive and open it with Google Sheets.
Sources and further reading
Our six steps, the cash, capacity and comfort grades and the Harbour Lane example are our own, worked out from UK government appraisal guidance, professional accounting and project management material, and what IT practitioners say about real server and cloud costs, rather than taken from any one template. Links open in a new tab.
- The Green Book: appraisal and evaluation in central government (HM Treasury)
- Green Book discount rate review 2026: HM Treasury response (HM Treasury)
- Annual Investment Allowance (GOV.UK)
- Cloud security guidance: choosing a cloud provider (National Cyber Security Centre)
- NPV function (Microsoft Support)
- Windows Server 2016 lifecycle (Microsoft Learn)
- Payback and discounted payback (ACCA technical article)
- Discounting and net present value, Challenges in advanced management accounting (The Open University, OpenLearn)
- Seven deadly sins of benefits management (Association for Project Management)
Harbour Lane IT Ltd, its server, its quotes and all its figures are fictional and illustrative. General information to help you structure a decision, not financial, tax or investment advice. Microsoft, Excel, SharePoint and Windows Server are trademarks of Microsoft; Google Drive and Google Sheets are trademarks of Google. Updated 21 November 2026.