A risk register is a living log of the things that could go wrong on a project, scored by how likely they are and how much damage they would do, with an owner and a plan for each. It is the single place you track and manage risk from the start of a project to its close. You can download a free, editable UK template in Excel and Word below, blank plus a worked example, with no email address required.
Key takeaways
- A risk register lists each risk, scores it as probability x impact, names an owner, and records what you will do about it. It is reviewed and updated continuously, not written once and filed.
- The core columns are: risk ID, description, category, probability, impact, risk score, owner, response, contingency, status, and the dates raised and last reviewed. We explain each one below.
- Score probability (1-5) times impact (1-5) to get a risk score from 1 to 25, then colour it green, amber or red on a simple heat map so the worst risks rise to the top.
- The register is the R in RAID (Risks, Assumptions, Issues, Dependencies) – the wider log many projects keep. A standalone risk register and the R column of a RAID log hold the same thing.
- Download the free Excel and Word template below – blank, plus a filled UK small-business example you can copy.
What is a risk register?
A risk register is a structured list of the risks identified on a project, kept up to date so you can track and manage them rather than be surprised by them. Each entry captures one risk: a short description of what could happen, how likely it is, how badly it would hurt the project, who owns it, and what the response is. The point is not paperwork. It is to make uncertainty visible and assigned, so that the three or four things most likely to derail the work are being actively managed by a named person, not left to chance.
It is a living document. New risks appear as the project moves; old ones close as they pass or are dealt with; scores change as circumstances change. A register that is written at the start and never opened again is doing none of its job. A good one is reviewed at every project checkpoint and updated the moment something shifts.
A note on jargon: a risk is something that might happen and would affect the project if it did – as opposed to an issue, which is a problem that has already happened. Probability (also called likelihood) is how likely the risk is; impact (also called severity) is how much damage it would do. The owner is the one person responsible for watching and managing that risk. We define the rest as we go.
What are the key columns in a risk register?
A risk register is only as good as its columns. Too few and you cannot prioritise; too many and nobody keeps it current. These are the columns that earn their place in a small-business or single-project register, and what each one holds.
| Column | What it holds |
|---|---|
| Risk ID | A short reference (R1, R2…) so you can talk about a risk without retyping it. |
| Risk description | One clear sentence: the cause and the effect. “Photography slips and delays the launch”, not “photography”. |
| Category | The type – schedule, technical, financial, supplier, resource – so you can spot clusters. |
| Probability (likelihood) | How likely it is, scored 1 (very unlikely) to 5 (very likely). |
| Impact (severity) | How much damage it would do, scored 1 (trivial) to 5 (severe). |
| Risk score | Probability times impact (1 to 25). This is what you sort on. |
| Owner | The one named person responsible for watching and managing it. Not a team. |
| Response / mitigation | What you will do to make it less likely or less damaging. |
| Contingency / fallback | Plan B if it happens anyway – the safety net. |
| Status | Open, mitigated, or closed. |
| Date raised / last reviewed | When it was added and when you last looked at it – proof the register is alive. |
What is the difference between probability and impact?
Probability and impact are the two halves of every risk score, and they answer different questions. Probability (likelihood) asks: how likely is this to happen at all? Impact (severity) asks: if it does happen, how much will it hurt? A risk that is near-certain but trivial scores low; a risk that is unlikely but would sink the project scores higher than you might expect. You multiply the two to get a single risk score, and that is what tells you where to spend your attention.
The simplest way to read those scores is a colour-banded grid – a heat map. Plot probability up one side and impact along the bottom, multiply at each cell, and colour the result green (low), amber (medium) or red (high). The red corner, top-right, is where high-probability meets high-impact: those risks get managed first.
The bands are a convention, not a law, but a common one for a 5 x 5 grid is: 1 to 6 green (monitor), 8 to 12 amber (active mitigation), 15 to 25 red (act now, escalate). Pick your bands once, write them at the top of the register, and apply them consistently. The Excel template below does the multiplication for you.
How does a risk register fit with RAID?
You will often hear a risk register mentioned alongside RAID – that stands for Risks, Assumptions, Issues, Dependencies, the four kinds of thing a project manager tracks. A RAID log is one document with four tabs or sections, and the risk register is the R: it is the risks tab of a RAID log. If your project is small, a standalone risk register is plenty. If it is larger, you may keep the full RAID log so that assumptions, live issues and dependencies on other teams sit alongside the risks. The risk content is identical either way.
| Letter | Tracks | In one line |
|---|---|---|
| R – Risks | Things that might happen | This register. Scored and owned. |
| A – Assumptions | Things taken as true for now | “The agency starts in July.” If it breaks, it becomes a risk or an issue. |
| I – Issues | Problems that have already happened | A risk that came true, now needs fixing. |
| D – Dependencies | Things you rely on others to deliver | “We cannot launch until the bank approves the merchant account.” |
A filled example: a UK small business
Most risk-register examples online are written for a US enterprise or use abstract placeholder risks. Here is a filled one for a real UK situation: a small homeware shop, Wren & Willow (an illustrative example, not a real firm), relaunching its tired website as a proper online shop. It is the same business we use across our project charter and other templates, so the risks join up. The scores are realistic for a project of that size.
| ID | Risk | P | I | Score | Owner | Response |
|---|---|---|---|---|---|---|
| R1 | Product photography slips and delays the launch | 4 | 4 | 16 | Ravi (PM) | Book photographer in June; shoot in two batches with a buffer week. |
| R2 | Till stock-sync with the new shop proves fiddly | 3 | 4 | 12 | Anna (Sponsor) | Test sync on 20 products before full load; reconcile daily in week one. |
| R3 | Web agency starts later than the quoted July date | 2 | 5 | 10 | Ravi (PM) | Confirm start date in writing; hold a backup agency on standby. |
| R4 | Card payment provider verification takes longer than expected | 2 | 3 | 6 | Anna (Sponsor) | Apply for the merchant account in week one, before the build needs it. |
| R5 | Part-time staff need more till training than planned | 3 | 2 | 6 | Ravi (PM) | Half-day training before launch; one-page crib sheet by the till. |
Read it top to bottom by score and the project’s real worry jumps out: R1, the photography, at 16. That is where Ravi spends his attention this week. R4 and R5, both green at 6, are noted and monitored but do not need managing today. That is the whole value of the register – it turns a vague sense of unease into a ranked, owned list. The full example, with the contingency and date columns, is in the downloadable files below.
Do you even need a risk register? A two-minute decision
Not every project needs a formal register. For a cost-conscious founder or a small team, the honest question is how much risk tracking the work actually warrants – and the answer for a quick job is “very little”. Use this to decide between a five-line list, a full register, or a RAID log.
The rule of thumb: if a project will spend real money, run for more than a few weeks, or depend on people and suppliers outside your control, keep a proper register. If it is small and quick, five lines in your notes carry the same discipline with none of the ceremony – what could go wrong, how bad, and what you will do. The register is a tool for managing risk, not a box to tick.
How often should you review a risk register?
Continuously, with a formal pass at every project checkpoint. In practice that means: glance at it each week, update a score the moment something changes, and do a proper top-to-bottom review at every milestone, stage gate or steering meeting. Close risks that have passed, add ones that have appeared, and re-score the ones still live. The “last reviewed” date column exists precisely so anyone can see at a glance whether the register is current or has quietly gone stale. A register nobody has touched in a month is telling you the project is not really managing its risks.
Download the free UK risk register template
Free, editable, no email required. Each file includes a blank register and the filled Wren & Willow example above, so you can see exactly how it is used. The Excel version works out the risk score for you and includes a scoring-key tab.
- Excel template (.xlsx) – register, worked example, and scoring key; the risk score is calculated automatically. Download Excel version
- Word template (.docx) – the same columns as a table you can type straight into. Download Word version
UK English, A4, designed for small businesses and single projects. Made by a practitioner, not a software vendor – there is nothing to sign up for.
The risk register is one of a set. Our project charter template names the headline risks at the outset and points to this register for the detail; the Project Initiation Document (PID) template covers the fuller PRINCE2 (PRojects IN Controlled Environments) version for larger or public-sector projects; and the lessons-learned template captures, at the end, which risks actually bit and what you would do differently next time.
Frequently asked questions
What is a risk register?
A risk register is a living log of the risks identified on a project, each scored by probability and impact, given an owner, and tracked with a planned response. It is the single place a project records and manages what could go wrong, reviewed and updated throughout the project rather than written once.
What are the key columns in a risk register?
Risk ID, description, category, probability, impact, risk score (probability times impact), owner, response or mitigation, contingency or fallback, status, and the dates it was raised and last reviewed. For a small project you can drop a column or two, but the score, the owner and the response are the ones you cannot lose.
What is the difference between probability and impact?
Probability (likelihood) is how likely a risk is to happen; impact (severity) is how much damage it would do if it did. You score each from 1 to 5 and multiply them for a risk score from 1 to 25. A risk needs both a high probability and a high impact to reach the red zone that demands action now.
What is the difference between a risk register and a RAID log?
A risk register tracks risks only. A RAID log (Risks, Assumptions, Issues, Dependencies) tracks four things in one document, and the risk register is its first section – the R. The risk content is the same; a RAID log also keeps assumptions, live issues and dependencies alongside it for larger projects.
Who owns the risk register?
The project manager owns the register as a whole and keeps it current. Each individual risk also has its own named owner – the person responsible for watching that risk and carrying out its response. On a small project the project manager may own most of the risks personally; on a larger one, ownership is spread across the team.
How often should you review a risk register?
Continuously, with a formal review at every project checkpoint or milestone. Update a score whenever something changes, and do a full pass at each stage gate or steering meeting – adding new risks, closing passed ones, and re-scoring the rest. The “last reviewed” date shows at a glance whether it is current.
What is the difference between a risk register and a risk assessment?
A risk assessment is usually a one-off study – common in health and safety – that identifies hazards and judges their risk at a point in time. A risk register is the ongoing, living log you keep and update across a project’s life. They overlap, but a risk assessment is a snapshot and a register is the running record.
This article is general guidance on project documentation, not formal project-management certification material, health-and-safety, legal or financial advice. The Wren & Willow example is illustrative. Adapt the template to your own organisation’s governance requirements. Updated 14 June 2026.