What Is a RASCI Matrix? The RACI Variant With a Support Role

Last updated: 12 June 2026

In short: a RASCI matrix is a RACI matrix with one extra role — S for Support. It maps every task on a project against the people involved, marking each person as Responsible (does the work), Accountable (owns it and signs it off), Support (actively helps the doer), Consulted (gives input first) or Informed (kept in the loop). The extra S earns its place when a task needs hands-on helpers as well as a lead. This guide explains how it works, when to use it instead of RACI, and includes a worked example and free Word and Excel templates.

Free RASCI matrix templates — no sign-up, no email. Both files contain the worked example from this guide plus a blank version to fill in for your own project.

→ Download the free Word template (.docx)
→ Download the free Excel template (.xlsx)

What is a RASCI matrix?

A RASCI matrix is a table that sets out who does what on a project. Down the side you list the tasks or deliverables; across the top you list the people, teams or roles; and in each cell you write a letter showing how that person is involved. It is a direct extension of the RACI matrix — same idea, same grid — with one role added: Support.

That single extra letter solves a problem RACI quietly creates. In RACI, anyone who is not doing the work, owning it or being informed gets labelled Consulted — even if they are actually pitching in and helping. RASCI separates the people giving an opinion (Consulted) from the people getting their hands dirty (Support), which on a small, stretched team is a distinction worth making.

RASCI is not a formal standard with a single author — it is an informal, widely used extension of RACI that grew up in project-management practice. There is no governing body for it, which means you will occasionally see the roles described slightly differently elsewhere; the version in this guide is the common one.

The five RASCI roles explained

  • R — Responsible. The person who does the actual work. A task can have more than one.
  • A — Accountable. The person who owns the outcome and signs it off. Exactly one per task.
  • S — Support. Someone who actively helps the Responsible person do the work, without owning it — a second pair of hands, not a second opinion.
  • C — Consulted. Someone whose input or expertise you need before the work is done. A two-way conversation.
  • I — Informed. Someone kept in the loop on progress or completion, but who does not feed into the work. One-way.

What the extra “S” really means: Support vs Responsible vs Consulted

This is the question every newcomer to RASCI actually has: when is someone Support rather than just Responsible or Consulted? The quickest test is to ask what they are contributing.

  • Support is active help with the task itself — doing part of the work, providing tools, data or hands-on time so the Responsible person can finish.
  • Support is not giving an opinion and walking away (that is Consulted), and it is not owning the outcome (that is Responsible or Accountable).

A quick example. Your bookkeeper is Responsible for migrating last year’s figures into a new accounting system. Your IT consultant logs in and runs the technical export and import alongside them — that is Support, not Consulted, because they are doing real work, not just advising. If the consultant had merely answered a question over the phone and left the bookkeeper to it, that would be Consulted.

One thing worth surfacing: Support has a cost. Marking someone Support commits real hours of their time, so the matrix is also a quiet capacity check. If one person is Support on eight tasks at once, you have found a bottleneck before it bites.

RASCI vs RACI: which should you use?

Use plain RACI when the work splits cleanly into people who do it, own it, advise on it and need to know about it. Add the S and use RASCI when there is a meaningful layer of hands-on helpers underneath the Responsible person — which is typical of small businesses where everyone mucks in, and of technical projects where a lead needs support staff.

A simple rule of thumb: if you find yourself wanting to mark several people Consulted on a task when they are really helping do it, that is your signal to switch to RASCI and mark them Support instead.

When to use RASCI (and when it is overkill)

RASCI is worth it when tasks routinely need both a lead and helpers, when you want to make team members’ supporting effort visible, or when blurred lines between advising and helping have caused friction before. It works just as well for the recurring, operational jobs of an established business — an annual audit, taking on a big new contract, a stocktake — as it does for one-off projects; you are mapping who does what, whatever the work happens to be. It is overkill, though, for short pieces of work where everyone already knows who is doing what — in that case RACI, or no matrix at all, is the right call. The tool exists to remove confusion; if there is none to remove, keep it in your back pocket.

How to build a RASCI matrix, step by step

  1. List your tasks. Write the main activities or deliverables down the left-hand column — one per row.
  2. List your people. Put the people, teams or roles across the top. Use roles rather than names where you can, so the matrix survives someone leaving.
  3. Assign Accountable and Responsible first. For each row, name the one person who owns it (A) and at least one who does it (R).
  4. Add Support. Mark the people actively helping the Responsible person with an S.
  5. Fill in Consulted and Informed. Add C for those whose input you need first, I for those who just need telling.
  6. Review and agree. Share it with the people named and let them challenge their own rows before the work starts.

The rules at a glance. Exactly one Accountable per task. At least one Responsible per task. Blank cells are fine — not everyone touches every task. Use job titles, not names, where you can. And do a quick sanity check: scan each column for anyone overloaded, and each row for a missing owner or doer.

Worked example: rolling out a cloud accounting system

Here is RASCI on a project where the Support role really matters: a small business moving its finances off spreadsheets and onto a cloud accounting system. There is a clear lead on each task, but also a lot of hands-on helping between the office manager, the bookkeeper and an external IT consultant.

Read the “Migrate existing data” row. The bookkeeper is Responsible — they own getting the figures right. The IT consultant is Support, because they are actively running the technical export and import alongside them, not just advising. On the very next row, “Configure users and integrations”, the roles flip: now the IT consultant is Responsible and the bookkeeper is Support. Same two people, different hats, depending on whose work it is.

Activity / DeliverableManaging DirectorOffice ManagerIT ConsultantBookkeeperStaffAccountant
Choose the accounting platformARCCIC
Agree the budget & sign it offA/RCCIIC
Migrate existing data into the systemIASRIC
Configure users, permissions & integrationsIARSII
Set up the chart of accountsIAIRIC
Train staff on the new systemIA/RSCII
Run a parallel month-endARSRIC
Sign off go-liveARCCIC
Decommission the old spreadsheetsIARCII
Post-go-live support & fixesIARSII
RASCI matrix for a small business rolling out a new cloud accounting system. The Support (S) cells show where someone actively helps the Responsible person without owning the task. Download the editable Word or Excel version below.

Notice every row has exactly one Accountable person, the Managing Director steps back to Informed once the detailed work begins, and Support appears only where someone is genuinely helping — not as a polite way of saying “interested”. A task can have more than one Responsible person, too: on “Run a parallel month-end” the office manager and the bookkeeper share the work, so both are marked R. Your own version will differ, but that shape is what you are aiming for.

Free RASCI matrix templates — no sign-up, no email. Both files contain the worked example from this guide plus a blank version to fill in for your own project.

→ Download the free Word template (.docx)
→ Download the free Excel template (.xlsx)

Common RASCI mistakes to avoid

  • Confusing Support with Consulted. The most common slip. If they are helping do the work, they are Support; if they are only advising, they are Consulted.
  • Too many people marked Support. Support commits real time. Marking half the team as helpers on every task makes the matrix meaningless and hides who is actually doing the work.
  • More than one Accountable per task. Two owners means no owner. Pick one.
  • Naming people instead of roles. Use job titles so the matrix survives staff changes.
  • Building it once and forgetting it. A RASCI matrix is a living document — revisit it when the project changes.

RASCI and the other responsibility models

RASCI is one of several variations on RACI. If a Support role is not quite what you need, it is worth knowing the alternatives: the CARS matrix is a simpler, action-focused option, while the DACI and RAPID® frameworks are built for making decisions rather than assigning tasks. Our guide to the RACI matrix is the best starting point if you are new to all of this.

Frequently asked questions

What does RASCI stand for?

RASCI stands for Responsible, Accountable, Support, Consulted and Informed. It is a RACI matrix with one extra role — Support — for the people who actively help do the work without owning it.

What is the difference between RASCI and RACI?

RASCI is RACI plus a Support (S) role. RACI has four roles; RASCI has five. The extra S marks people who roll up their sleeves and help the Responsible person, rather than just being consulted for an opinion. Everything else works the same way.

What is the difference between Support and Consulted?

A Consulted person gives input or an opinion before the work is done, then steps back. A Support person actually helps carry the work out alongside the Responsible person. Consulted is advice; Support is hands-on effort.

Can one person be both Responsible and Accountable in RASCI?

Yes. In a small business this is common — mark the cell A/R. The rule that each task has exactly one Accountable person still applies.

Is RASCI better than RACI?

Neither is better in the abstract. RASCI is more useful when tasks genuinely need hands-on helpers as well as a lead, which is common in small, stretched teams. If no one is doing meaningful Support work, plain RACI is simpler and just as clear.

How many people can be Support on one task?

As many as genuinely help, but be honest about it. If half the team is marked Support on every task, the matrix has stopped meaning anything. Reserve S for people doing real, hands-on work.