Scope Statement Template: Free UK Word + Example (In & Out of Scope)

A project scope statement is a short document that sets out exactly what a project will deliver and, with equal weight, what it will not. It lists the objectives, the deliverables, what is in scope and what is out of scope, plus the constraints and assumptions everyone is working to. Agree it, get the sponsor to sign it, and you have a boundary you can point to whenever someone asks for “one more small thing”. You can download a free, editable UK Word template below, with a worked small-business example filled in. No email address required.

Key takeaways

  • A scope statement answers three questions: what are we delivering, what are we deliberately not delivering, and how will we know it is done.
  • The “out of scope” list is the part that prevents scope creep. Anything you fail to exclude on paper is an argument you will have later.
  • Ten sections cover it: project details, objectives, scope description, in scope, out of scope, deliverables, acceptance criteria, constraints, assumptions and sign-off — plus a one-page scope matrix.
  • In the UK, a scope statement is the PMI (American) term. PRINCE2 splits the same job across the Project Brief and the Project Initiation Document (PID). We map them below.
  • For a very small job you may only need a one-paragraph version. We show you how to right-size it.
  • Download the free Word template below — blank, plus a filled UK example. It opens in Microsoft Word and in Google Docs.

Download the free UK scope statement template

Free, editable, no email required. Includes a blank template and the filled Wren & Willow worked example below, so you can see exactly how it is used.

  • Word template (.docx) — the full scope statement plus a scope matrix, ready to type into.
  • Opens in Microsoft Word and in Google Docs (open it from Google Drive, or use File > Open).

Download the Word template

UK English, A4, made for small businesses by a practitioner — there is nothing to sign up for.

Project ManagementInitiationFree template

What is a project scope statement?

A project scope statement is a brief, agreed document that defines the boundary of a project: the work it will do, the work it will not do, and the conditions for calling each deliverable finished. It is written early, during initiation and planning, and it is signed off by the sponsor — the person funding the work — before detailed work begins.

Its real job is to make the boundary explicit. Most project disputes are not about the work inside the boundary; they are about whether some new request was ever part of the deal. A scope statement settles that in advance, in writing, so the answer is a document rather than a memory.

A note on jargon: the sponsor is the budget holder who owns the project’s success. A deliverable is a tangible thing the project hands over. Scope creep is the slow expansion of a project beyond what was agreed, usually one small unbudgeted request at a time. We define the rest as we go.

In scope and out of scope: the boundary that stops scope creep

Every scope statement has two lists that matter more than the rest: what is in scope, and what is out of scope. The in-scope list is the work you have agreed to do. The out-of-scope list is the work you are deliberately not doing — and it is the single most useful thing in the document.

Here is why. A request that is not on either list becomes a debate. A request that is named on the out-of-scope list becomes a change request, handled through change control, with its own cost and timeline. The exclusion you wrote down is what turns “but I assumed that was included” into “that is a change, here is what it costs”. If it is not written here, you cannot point to it later.

In scope and out of scope: the boundary a scope statement drawsThe In scope box contains the work being delivered. The Out of scope box lists what is explicitly excluded. The line between them is the agreed scope boundary; once signed, anything crossing it is a change request.The scope boundaryIN SCOPEWhat the project will deliver✓ CRM set up for six sales users✓ Import contacts and open quotes✓ Build the quote-to-order pipeline✓ Half a day of training per user✓ Thirty days of go-live supportOUT OF SCOPEExcluded — each one is a future change request✕ Xero / invoicing integration✕ Email marketing automation✕ Workshop scheduling system✕ Archived jobs over three years✕ Custom reports beyond the dashboardThe signed scope statement is this boundary line — change control defends it.Anything that crosses from right to left is a change request, not a free extra.
The scope statement draws a boundary. The out-of-scope list on the right is what keeps work from drifting across it unbudgeted.

Anything you fail to exclude on paper is an argument you will have later.

The ten sections of a scope statement (and how to fill each one)

Our template has ten sections plus a scope matrix. Work through them in order; each one is a heading the detailed plan will later expand.

  1. Project details. Name, sponsor, project manager, date and version. The version number matters — “v1.0 approved” is the one people sign against.
  2. Objectives. Two or three measurable outcomes the project must achieve. Make them specific: “cut quote turnaround from five working days to two”, not “improve quoting”.
  3. Product or solution scope description. In plain English, what is being built or changed, and the high-level requirements it must meet.
  4. In scope. One line per item of work that IS being delivered. Be specific enough that two people would read each line the same way.
  5. Out of scope. The exclusions. Name anything a reasonable person might assume is included but is not. This is the section people skip and then regret.
  6. Key deliverables. The tangible outputs, each with an owner and a date. A deliverable is something you can hand over and tick off.
  7. Acceptance criteria. How the sponsor will judge each deliverable as done. Make them testable: “all six users can create a quote unaided”, not “users are happy”.
  8. Constraints. The fixed limits — budget, deadline, resources, technology, policy. The things you cannot move.
  9. Assumptions. What you are taking to be true for planning. If an assumption turns out to be false, the scope may have to change — which is exactly why you list them.
  10. Sign-off. The sponsor signs. From that point, the scope is baselined and any change goes through change control.

The scope matrix: a one-page in-or-out summary

A scope matrix is a small table that lists every significant deliverable or area down the left, with two columns — included and excluded — and a notes column. It is the fastest way for a busy sponsor to scan the boundary in ten seconds, and it forces you to make a yes-or-no call on each area rather than leaving it vague. Our Word template includes a scope matrix on both the blank page and the worked example.

Deliverable / areaIncludedExcludedNotes
CRM setup (6 users)YesCore of the project
Data import (contacts, open quotes)YesLast three years only
Xero / invoicing integrationYesPossible phase 2
Email marketing automationYesNot needed now

Worked example: a CRM rollout for a UK small business

The template comes with a filled example so you are not staring at a blank page. It follows Wren & Willow Ltd, a fictional 22-person UK kitchen-and-joinery firm replacing spreadsheets and email with a shared CRM (customer relationship management) system. The figures are illustrative but realistic for a project of this size.

Wren & Willow CRM rollout — the boundary, in brief

Objective: hold every customer, quote and job in one shared system by 30 September 2026, and cut quote turnaround from five working days to two.

In scope: set up the CRM for six sales users, import contacts and open quotes, build the quote-to-order pipeline, train each user for half a day, and provide thirty days of go-live support.

Out of scope: accounts and invoicing (these stay in Xero, with no integration in this phase), the workshop scheduling system, email marketing automation, archived jobs over three years old, and custom reports beyond the standard dashboard.

Constraints: a budget of £4,800 (£1,560 software in year one, £3,240 setup and training) and a hard deadline of 30 September, before the autumn sales push.

Notice what the out-of-scope list does here. Xero integration is the request most likely to appear halfway through (“while you are at it, can the CRM talk to our accounts?”). Because it is named as excluded, it is handled as a costed phase-two change rather than absorbed for free into a fixed-price project. That single line can be the difference between a project that lands on budget and one that quietly doubles in effort.

Download the free Word template (blank + this example)

How a scope statement relates to the brief, the charter, the PID and change control

This is the part most guides skip, and it matters if you work in the UK. The same job goes by different names depending on which method your organisation follows.

DocumentWhat it doesHow scope fits
Project charter / Project BriefAuthorises the project and sets its direction in one to three pages. “Charter” is the PMI (American) term; “Project Brief” is the PRINCE2 (British) term.Contains a high-level scope summary. The scope statement is the fuller version of that section.
Project Initiation Document (PID)The detailed PRINCE2 document that follows the brief, adding governance, risk and reporting controls.The PID’s “project product description” and scope section do the scope statement’s job inside a larger document.
Statement of work (SOW)A contractual scope document used between a buyer and a supplier, with deliverables, timelines and payment terms.A scope statement is internal; an SOW is the contractual version you would attach to a supplier agreement.
Work breakdown structure (WBS)Breaks the in-scope work into a hierarchy of tasks.The WBS expands what the scope statement says is in scope; it never adds new scope of its own.

Change control is what keeps the boundary honest. A scope statement is only as good as the discipline behind it. Once the sponsor signs, the scope is baselined. After that, any new request is logged as a change request, assessed for cost and impact, and either approved or declined — usually recorded on a RAID log (risks, assumptions, issues and dependencies) or a dedicated change log. The out-of-scope list is what gives you the clean, unarguable answer: “that is outside the agreed scope, so it goes through change control.” Without the written boundary, every request is a negotiation. With it, every request has a process.

Do you even need a full scope statement? Right-sizing it

Not every project needs a ten-section document. The right amount of paperwork is the least that prevents the argument you would otherwise have. Use this ladder to pick the right size.

  1. A one-paragraph scope note — for a small, internal job of a few days with one owner. Three sentences: what we are doing, what we are not, and what “done” looks like. Often enough.
  2. A one-page scope statement — for a project with a budget, a deadline and more than one person involved. Use our template but keep each section to a line or two. This is the sweet spot for most small-business projects.
  3. A full scope statement plus a scope matrix — for anything with an external supplier, a fixed price, or a sponsor who needs to sign. The matrix earns its place here.
  4. A statement of work (SOW) — when money changes hands between two organisations. Take the scope statement and add commercial terms, then have it reviewed before signing.

If you are watching every pound, the honest answer is that a free template and an hour of thought will protect you better than any paid tool. The value is in writing the exclusions down, not in the software you write them in.

Common mistakes that let scope creep in

  • An empty out-of-scope list. The most common and most expensive mistake. If you exclude nothing, you have agreed to everything by implication.
  • Vague in-scope lines. “Sort out the website” can mean a tweak or a rebuild. Write lines two people would read identically.
  • No acceptance criteria. Without a testable definition of done, deliverables drift and “finished” becomes a matter of opinion.
  • Never signed. An unsigned scope statement is a draft. The signature is what makes it the baseline change control can defend.
  • Filed and forgotten. The document only works if you actually point to it when a request arrives. Keep it where the team can find it.

Want the change-control side as well?

The free Word template above protects the boundary at sign-off. If you also want the tools that defend it afterwards, our £19 Scope & Change pack adds a change-request form, a change log, a scope-change impact assessment and a scope matrix in Word and Excel — the documents you reach for when the requests start arriving.

Optional. The free template stands on its own; the pack is for teams that want the full change-control set in one place.

Frequently asked questions

What is a project scope statement?

A project scope statement is a short, agreed document that defines what a project will deliver, what it will not deliver (its exclusions), and how each deliverable will be judged complete. It is written during initiation and signed off by the sponsor before detailed work begins.

What are the components of a scope statement?

Project details, objectives, a product or solution scope description, an in-scope list, an out-of-scope list, key deliverables, acceptance criteria, constraints, assumptions and sign-off — plus a one-page scope matrix that summarises what is included and excluded.

What is the difference between in scope and out of scope?

In scope is the work the project has agreed to deliver. Out of scope is the work it is deliberately not delivering. The out-of-scope list is what prevents scope creep, because anything named there is handled as a change request rather than assumed to be included.

How does a scope statement prevent scope creep?

By naming exclusions in writing and getting them signed off, it converts later “small” requests into change requests with a cost and a decision. The written boundary gives you a document to point to instead of a memory to argue over.

What is the difference between a scope statement and a statement of work (SOW)?

A scope statement is an internal document that defines a project’s boundary. A statement of work is the contractual version used between a buyer and a supplier, adding deliverables, timelines and payment terms. The SOW is what you attach to an agreement when money changes hands.

What is the difference between a scope statement and a project charter?

A project charter authorises the project and sets its direction in one to three pages, including a high-level scope summary. The scope statement is the fuller, more detailed version of that scope section. The charter comes first.

Do you need a scope statement for a small project?

Not always a full one. For a few-day internal job, a one-paragraph scope note may be enough. For anything with a budget, a deadline or more than one person involved, a one-page scope statement is worth the hour it takes. The exclusions are the part you should never skip.

Who writes and signs off the scope statement?

The project manager usually writes it, often with the sponsor. The sponsor approves and signs it. In larger organisations a steering group or project board may also sign off before the scope is baselined.

If you also need the documents that sit around the scope statement, our project charter template covers the one-page authorisation, the PID template covers the fuller PRINCE2 version, the project proposal template helps you pitch the work, and the work breakdown structure template expands the in-scope work into tasks.

Written by Linda Garrould. This article is general guidance on project documentation, not formal project-management certification material or legal advice. Adapt the template to your organisation’s own governance. Updated 15 June 2026.