RAID Log Template: Free UK Excel & Word + Example

A RAID log is a single document that tracks four things in one place: Risks (what might go wrong), Assumptions (what you are taking as true but have not confirmed), Issues (problems happening now), and Dependencies (things your project relies on, often from outside the team). It is the project manager’s running notebook of everything that could affect delivery. You can download a free, editable UK template in Excel and Word below, with a worked example filled in. No email address required.

Key takeaways

  • RAID stands for Risks, Assumptions, Issues and Dependencies — four lists kept in one place.
  • It is the umbrella document. A full risk register is the deeper version of only the Risks section.
  • For a small project, one RAID log is enough — it beats keeping four separate registers you have to cross-check.
  • The Risks section should score each risk by probability multiplied by impact. In our Excel template that score is a live formula, not a number you type.
  • Download the free Excel and Word template below — blank, plus a filled UK small-business example.

What is a RAID log?

A RAID log is a structured list a project manager keeps to record and monitor the four kinds of thing that can affect a project. The name is an acronym: Risks, Assumptions, Issues and Dependencies. Each gets its own section, and the whole thing lives in one spreadsheet or document so nothing falls through the cracks.

Its job is visibility. Instead of risks living in one person’s head, assumptions going unspoken, issues being firefought by email, and dependencies surfacing only when they slip, a RAID log puts all four where the team and the sponsor can see them, with an owner and a status against each. It is reviewed regularly — usually at every project meeting — and updated as things change.

A note on the acronym. You will see RAID expanded differently across the web. Some large US tools render the A as “Actions” and the D as “Decisions”. In UK and PRINCE2 (PRojects IN Controlled Environments, version 2) practice, the standard reading is the one we use throughout: Risks, Assumptions, Issues, Dependencies. If a colleague means actions or decisions, those are worth tracking too, but they are usually kept in an action log and a decision log rather than confused with the RAID.

What does each letter mean?

The four sections answer four different questions. Keeping them separate is the point: a risk is not an issue, and an assumption is not a dependency, even though teams routinely muddle them.

The four parts of a RAID logRRisksThings that MIGHT happen andwould hurt the project if they did.e.g. “the supplier may miss August”AAssumptionsThings you are taking as TRUEthat you have not confirmed.e.g. “the agency starts in July”IIssuesProblems happening NOW thatneed action, not only watching.e.g. “card verification is stuck”DDependenciesThings the project RELIES on,often from outside the team.e.g. “broadband upgrade from landlord”The test: a risk MIGHT happen; an issue HAS happened. An assumption is yours to confirm; a dependency is someone else’s to deliver.

  • Risks are things that might happen and would hurt the project. They live in the future and carry a probability. “The product photography could overrun and slip the launch” is a risk.
  • Assumptions are things you are treating as true but have not actually confirmed. They are quietly dangerous because nobody questions them. “We assume the web agency can start in July” is an assumption — until you have it in writing.
  • Issues are problems happening right now. A risk that comes true becomes an issue. Issues need an action and an owner today, not monitoring. “The card provider has not verified our account” is an issue.
  • Dependencies are things your project needs that are often outside your control — another team, a supplier, a landlord, a piece of infrastructure. “We depend on the landlord’s broadband upgrade before we can take card payments” is a dependency. Dependencies run in two directions: inbound, where you are waiting on someone else’s output, and outbound, where another team is waiting on yours — both belong in the log.

What columns does a RAID log need?

Each of the four sections holds slightly different information, because you manage each differently. A risk needs a score and a mitigation; an issue needs an action and a date; a dependency needs to know who it relies on and when it is needed. These are the columns our template uses.

SectionColumns it uses
RisksDescription, probability (1–5), impact (1–5), score (probability × impact), owner, mitigation, status
AssumptionsDescription, validity / confidence, owner, action if it proves false
IssuesDescription, severity, owner, action, status, date raised
DependenciesDescription, depends on whom, needed by, status

The one column worth dwelling on is the risk score. It is probability multiplied by impact, each rated one to five, giving a number from 1 to 25. That number is what lets you sort the list so the worst risks sit at the top, and it drives the familiar RAG (red/amber/green) status: green for 1–6 (low), amber for 7–14 (medium) and red for 15–25 (high). In our Excel template the score is a live formula — type a probability and an impact, and the score and its red/amber/green colour appear on their own. You never type the score, which means it can never be wrong or go stale.

How does a RAID log relate to a risk register?

This is the question that trips people up. The short answer: the RAID log is the umbrella, and a risk register is the detailed, expanded version of only its Risks section. On a small project you do not need both — the Risks part of the RAID log is your risk register. On a large or high-risk project, the Risks section grows its own dedicated document with deeper columns (root cause, contingency, residual risk, review dates), and that document is the risk register.

How RAID relates to the risk registerRAID log (the umbrella)RisksAssumptionsIssuesDependenciesFull risk registerthe Risks section, expanded on bigger projectsSmall project: the Risks section is your risk register.Big project: it grows into a standalone register.

So the decision is about size, not principle. Keep one RAID log for as long as it serves you. Split the Risks section out into a separate risk register only when the risk detail outgrows a single column of notes. Most small-business projects never need to.

One RAID log or four separate registers?

If you have read about risk registers, issue logs, assumption logs and dependency maps as four separate documents, you may be wondering which to keep. For most small projects the answer is firmly: one RAID log. Four separate registers means four files to open, four to keep in step, and four chances for something to be updated in one place and not another.

The single RAID log wins because it is reviewed in one pass at each meeting, the four lists sit next to each other so you can see how they interact (a dependency that slips becomes a risk; a risk that lands becomes an issue), and there is only ever one version to trust. Split into separate registers only when a project is large enough that a single section needs more room than a shared document gives it — and even then, usually only the Risks section earns its own file.

A filled example: a UK small business

Most RAID examples online are abstract or describe a large enterprise programme. Here is a filled one for a real UK situation: a small homeware shop, Wren & Willow (an illustrative example, not a real firm), relaunching its tired website as a proper online shop. One row is shown per section to keep it readable; a live project would have several in each.

TypeDescriptionKey detailOwnerStatus
RiskProduct photography overruns and slips the launch.Probability 3 × impact 4 = 12 (amber). Mitigation: book the photographer for two fixed days in August.RaviOpen
AssumptionThe web agency will start in July, as quoted.Confidence: medium. Action if false: bring forward the backup agency conversation now.AnnaTo confirm
IssueThe card provider has not yet verified the business account.Severity: high. Action: send the outstanding ID documents today; chase Friday. Raised 10 June.RaviIn progress
DependencyFaster broadband from the landlord, needed for the in-store card terminal.Depends on: the landlord’s contractor. Needed by: 20 September.AnnaAwaiting date

Read across the rows and the project’s whole risk picture is visible at a glance: one thing that might go wrong, one belief to test, one fire to put out today, and one thing waiting on somebody else. That is a RAID log doing its job — and it is exactly what the downloadable template gives you, blank and filled.

How do you use and maintain a RAID log?

  1. Set it up at the start. Create the four sections at project kick-off and seed each with whatever you already know. Even three entries beats a blank page.
  2. Give every entry an owner. A line with no name against it will not be acted on. Name a person, not a team.
  3. Review it at every project meeting. Walk the four sections in order. Close what is done, add what is new, re-score risks whose probability has changed.
  4. Promote and demote between sections. A risk that materialises moves to Issues. A dependency that slips spawns a risk. This movement is the log working as intended.
  5. Keep the risk scores honest. Because the score is a formula in the Excel template, you only ever change probability and impact; the score and its colour update themselves.
  6. Keep one version. One file, shared, with a single owner who curates it. Avoid emailing copies around — that is how versions drift.

Who maintains it, and how often should it be reviewed?

Who maintains it: the project manager owns the RAID log, but the whole team feeds it. Anyone can raise a risk, flag an issue or question an assumption; the project manager curates and keeps it tidy. How often: review it at every project meeting — weekly on an active project — and update it the moment something material changes rather than waiting for the next meeting. A RAID log that is only touched monthly has usually stopped being used.

Common mistakes to avoid

A RAID log fails in predictable ways, and nearly all of them come down to the log drifting away from how the project actually runs.

  • Entries with no owner. A risk or issue with no name against it belongs to nobody and gets actioned by nobody. Name a person, never a team.
  • Vague descriptions. “Supplier risk” tells a reader nothing. Spell out what might happen, by when, and what the effect would be — as the Wren & Willow rows above do.
  • Logging an issue as a risk. If it has already happened it is an issue, and it needs an action today, not a probability score. Scoring something that is already true wastes the score.
  • Leaving closed items in place. Mark things done and move them out of the way, or the log fills with noise and people stop trusting it.
  • Writing it once and filing it. A RAID log only earns its keep if it is reviewed at every meeting. One that is never reopened is just documentation for its own sake.

Download the free UK RAID log template

Free, editable, no email required. Each file includes a blank RAID log and the filled Wren & Willow example above, so you can see exactly how it is used. The Excel version scores risks with a live probability × impact formula, colour-codes the score red/amber/green, and gives you 1–5 dropdowns.

  • Excel template (.xlsx) — four clearly separated sections, the live risk-score formula, conditional formatting and dropdowns. Download Excel version
  • Word template (.docx) — the same four sections as tables, for teams who prefer a document. Download Word version

UK English, A4, designed for small businesses. Made by a practitioner, not a software vendor — there is nothing to sign up for.

The RAID log pairs naturally with a few other documents. The risk register template is the detailed version of the Risks section, for when a project outgrows a single column. The project charter template sets the project’s direction and authorises it in the first place, and the lessons learned template captures what the RAID log taught you once the project closes.

Frequently asked questions

What is a RAID log?

A RAID log is a single document a project manager uses to track four kinds of thing that can affect a project: Risks, Assumptions, Issues and Dependencies. Each has its own section with an owner and a status, and the log is reviewed at every project meeting so nothing is forgotten.

What does RAID stand for?

Risks, Assumptions, Issues and Dependencies. Some US tools expand the A as “Actions” and the D as “Decisions”, but in UK and PRINCE2 practice the standard reading is Risks, Assumptions, Issues, Dependencies.

What is the difference between a RAID log and a risk register?

A RAID log tracks all four categories — risks, assumptions, issues and dependencies — at a high level. A risk register covers only risks, but in much more depth. The risk register is the expanded version of the RAID log’s Risks section; on a small project, the Risks section of your RAID log is your risk register.

What is the difference between a risk and an issue?

A risk is something that might happen in the future and would harm the project if it did, so it carries a probability. An issue is a problem happening now that needs action today. When a risk comes true, it stops being a risk and becomes an issue.

Who maintains the RAID log?

The project manager owns and curates it, but the whole team contributes. Anyone can raise a risk, flag an issue or question an assumption; the project manager keeps it accurate and tidy.

How often should a RAID log be reviewed?

At every project meeting, which on an active project usually means weekly, and updated immediately whenever something material changes. A RAID log that is only reviewed monthly has usually fallen out of use.

Do I need a RAID log and a risk register, or only one?

For most small projects, one RAID log is enough — its Risks section does the job of a risk register. Keep them separate only on large or high-risk projects, where the Risks section needs more detail than a shared document can hold.

Can you use a RAID log in Agile?

Yes. Scrum has its own ceremonies, but many agile and hybrid teams still keep a RAID log at project or programme level to track cross-team dependencies, standing assumptions and longer-running risks that a sprint board is not designed to hold. It complements the backlog rather than competing with it.

This article is general guidance on project documentation, not formal project-management certification material or legal advice. The Wren & Willow example is illustrative. Adapt the template to your organisation’s own governance requirements. Updated 16 June 2026.