Project Status Report Template: Free UK Word & Excel + Example

A project status report is a short, regular update on how a project is going against its plan — its overall health, what has been done, what is next, and what needs attention. It is usually one page, sent weekly or monthly, and uses a simple Red/Amber/Green rating so a reader can take in the position at a glance. You can download a free, editable UK template in Word and Excel below, with a worked example filled in. No email address required.

Key takeaways

  • A status report answers four questions: how healthy is the project, what got done this period, what is next, and what needs a decision or help.
  • It is built around a RAG status (RAG = Red/Amber/Green): Green means on track, Amber means at risk and needing attention, Red means off track and needing action. Many teams now use BRAG, which adds Blue for completed work — a growing variant (see below).
  • The core sections: reporting period, overall RAG status, progress this period, progress against the plan, budget, key risks and issues, next steps, and decisions or help needed.
  • Keep it to one page. The discipline is leaving things out — a status report is a one-pager, not a ten-page report.
  • Download the free Word and Excel template below — blank, plus a filled UK small-business example. The Excel version has a BRAG dropdown (Blue/Red/Amber/Green) that colours itself.

What is a project status report?

A project status report is a brief, regular update that tells stakeholders how a project is doing against its plan. It records the project’s overall health, the progress made since the last report, what is coming up next, and anything that needs a decision or a hand. Its job is communication: it keeps the sponsor, the team and anyone watching from the side aligned without a meeting, and it creates a written trail of how the project tracked over time.

Think of it as a regular health check. Where a project plan sets out the route, the status report says where you have got to on that route this week or this month, and whether you are on time, at risk, or in trouble. A good one can be read in two minutes and acted on without a follow-up call.

A note on jargon: a stakeholder is anyone with an interest in the project — the sponsor, the team, a customer. The sponsor is the senior person funding the work. A milestone is a significant checkpoint, such as a launch date. We define the rest as we go.

What goes in a project status report?

A status report that earns its keep has eight short sections. Lead with the date and the overall rating so a busy reader gets the headline first, then fill in the detail underneath.

  1. Reporting period and date. What window the report covers, for example “week ending 14 September” or “September 2026”, and who prepared it.
  2. Overall status (RAG). One colour — Red, Amber or Green — for the whole project, with a sentence saying why. This is the part most people read first.
  3. Progress this period. What actually got done since the last report. Be specific: “120 of 150 products loaded”, not “good progress made”.
  4. Progress against the plan. How that compares with where the plan said you would be. Name the milestones hit, missed or slipping.
  5. Budget status. Its own RAG colour and a line on spend against budget. Money problems rarely announce themselves, so report them early.
  6. Key risks and issues. The handful of things most likely to derail the project (risks) and the problems already biting (issues). Three or four, not a full register.
  7. Next steps / upcoming. What happens before the next report. This is what the reader uses to hold the project to account.
  8. Decisions or help needed. Anything you need from the sponsor or stakeholders, with a date. A status report that never asks for anything is usually hiding something.

Anatomy of a one-page status report1 · Reporting period & dateThe window, and who prepared it2 · Overall statusOne BRAG/RAG colour overall3 · Progress this periodWhat actually got done4 · Progress against the planMilestones hit, missed, slipping5 · Budget statusIts own RAG · spend vs budget6 · Key risks & issuesThe 3–4 that matter most7 · Next steps / upcomingBefore the next report8 · Decisions / help neededWith a date, from the sponsor

What does RAG status mean?

RAG stands for Red, Amber, Green — a traffic-light rating that lets a reader judge a project’s health in a single glance. It is the most widely used status convention in UK project management, and it is the heart of a good status report. Each colour has a settled meaning.

What the colours meanGreen — on trackOn schedule and within budget. No action needed beyond carrying on.Amber — at riskSlipping or threatened. Needs attention now to stop it turning red.Red — off trackBehind, over budget or blocked. Needs a decision or intervention.

The trick with RAG is honesty. The temptation is to rate everything Green to avoid awkward conversations, but a report that stays Green right up until the project fails is worse than useless. Amber is the most valuable colour: it flags trouble while there is still time to act. Give the project one overall colour, and consider a separate colour for time, budget and scope if your reader wants more detail.

RAG or BRAG? Why many teams now add Blue

BRAG adds a fourth colour — Blue — to RAG, and it is a growing variant, used by some UK programme and PMO (project management office) teams alongside the default RAG. Blue marks work that is complete: delivered, signed off and no longer needing attention. Red, Amber and Green keep their usual meanings.

What the colours mean (BRAG)Blue — completeDelivered and signed off. Done, so it no longer needs watching.Green — on trackIn progress, on schedule and within budget. Carry on.Amber — at riskSlipping or threatened. Needs attention now to stop it turning red.Red — off trackBehind, over budget or blocked. Needs a decision or intervention.

Why the shift to BRAG? Under plain RAG, anything finished stays Green — so a long project becomes a wall of green that mixes “done and dusted” with “still on track”, and the reader cannot tell at a glance how much is genuinely left to do. That is how “green creep” hides real risk: when almost everything is green, nobody scrutinises the few lines that are not. Blue lifts the completed work out of the picture, so Green comes to mean only “in progress and on track”, and the report shows the true size of what remains. On a longer programme where deliverables close one by one, that distinction earns its place.

One caveat worth knowing: the meaning of Blue is not universal. Most UK teams use it for complete, but a minority use it for ahead of plan or exceeding expectations. Whichever you adopt, put a short colour key on the report so every reader reads it the same way. The Excel template below ships with a BRAG dropdown, so you can use Blue, Red, Amber and Green out of the box — or stay with RAG if that is all your project needs.

Weekly or monthly? How often to send one

How often you report depends on how fast the project is moving and who is reading. There is no single right answer, but there is a sensible default for most small projects.

FrequencyBest forReader
WeeklyActive delivery, fast-moving work, anything currently at risk.The team and close stakeholders.
FortnightlySteady projects where a week brings little change.Project manager and sponsor.
MonthlySlower or longer programmes; board and senior reporting.Sponsor, steering group, board.

The practical rule: report weekly while a project is in active delivery or sitting at Amber or Red, and step down to monthly for the calmer stretches and for senior or board audiences, who want the shape of things rather than the week-by-week. Whatever cadence you pick, keep it regular — a report that lands on the same day each week earns far more trust than one that appears only when there is bad news.

A filled example: a UK small business

Most status-report examples online are screenshots from a software vendor or describe a large IT programme. Here is a complete one for a real UK situation: a small homeware shop, Wren & Willow (an illustrative example, not a real firm), partway through relaunching its tired website as a proper online shop. This is the report for the week before its planned soft launch.

ProjectWren & Willow online shop relaunch
Report date / periodWeek ending 14 September 2026 · prepared by Ravi (project manager)
Overall statusAmber — on course for the soft launch on 15 September, but product photography is running a few days late.
Progress this periodPayment setup tested and working. 120 of 150 products loaded. Staff training booked for 12 September.
Progress vs planSoft launch (15 Sep) on track. Photography milestone slipped from 10 Sep to 13 Sep.
Budget statusGreen — £5,900 of the £6,500 build budget committed; £600 and the £1,000 contingency remain.
Key risks & issuesRisk (Amber): the till stock-sync is still being tested; a fault here would delay go-live. Issue: photographer availability has tightened the photo window.
Next stepsFinish stock-sync testing by 13 Sep · load the final 30 products · run staff training · soft launch 15 Sep.
Decisions / help neededSponsor decision by 12 Sep: go ahead with soft launch if two products still lack photos, or hold for the full set?

Notice how much the colour does. A reader sees Amber overall and Green on budget and knows in a second that the money is fine but the timeline needs watching. Everything below explains those two colours and asks for the one decision that matters. That is a status report doing its job. (Under BRAG, the finished payment setup would show Blue, leaving Green to mean only the work still in progress and on track.)

How short should it be? Keep it to one page

The single most common mistake with status reports is making them too long. A status report is a one-pager, not a ten-page report — and the discipline is in what you leave out. A reader who has to scroll through three pages to find the RAG status will stop reading, which defeats the purpose. For a cost-conscious founder or a small team, the brief version is not a cut corner; it is the better document.

Keep out the things that belong elsewhere: the full task list (that is the plan), the complete risk register (link to it, do not paste it), and long narrative explanations. If a section needs more than a few lines, it probably needs a separate conversation, not more words in the report. The aim is a page someone can read standing up.

How to write a project status report, step by step

  1. Set the RAG status first. Decide the one honest overall colour before you write anything else; the rest of the report explains it.
  2. State the period and date. Make it obvious what window the report covers and when it was written.
  3. List what got done, specifically. Numbers and named milestones, not adjectives. “120 of 150 loaded” tells the reader something; “good progress” does not.
  4. Compare against the plan. Say where you should be by now and whether you are ahead, on, or behind. This is the part that turns a diary into a status report.
  5. Flag risks and the help you need. Name the three or four real risks, and put any decision you need from the sponsor in writing, with a date.
  6. Send it on the same day, every time. A predictable rhythm builds trust. Reliability is half of what a status report is for.

Write to be skimmed. Bold the section labels, lead with the colour, and resist the urge to soften bad news into Green — the value of the report is that people can trust it.

Download the free UK project status report template

Free, editable, no email required. Each file includes a blank one-page report and the filled Wren & Willow example above, so you can see exactly how it is used.

  • Word template (.docx) — the one-page report, ready to type into. Download Word version
  • Excel template (.xlsx) — the same fields, with a BRAG dropdown (Blue/Red/Amber/Green) that colours the cell to match, on both the blank and example tabs. Download Excel version

UK English, A4, designed for small businesses. Made by a practitioner, not a software vendor — there is nothing to sign up for.

A status report reports progress against the plan, so it works best alongside the documents either side of it. Our project plan template is what the report measures against; the project-on-a-page template covers very similar ground in a different, single-page visual format for senior audiences; the risk register template holds the full list of risks the report only summarises; and the project charter template is where the project was authorised in the first place.

Frequently asked questions

What is a project status report?

A project status report is a short, regular update on how a project is going against its plan. It covers the project’s overall health (usually a Red/Amber/Green rating), what was done this period, what is coming next, and anything that needs a decision. It is normally one page, sent weekly or monthly.

What goes in a project status report?

Eight sections: the reporting period and date, the overall RAG status, progress this period, progress against the plan, budget status, key risks and issues, next steps, and any decisions or help needed. Lead with the date and the overall colour so the reader gets the headline first.

What does RAG status mean?

RAG stands for Red, Amber, Green — a traffic-light rating of a project’s health. Green means on track, Amber means at risk and needing attention, and Red means off track and needing action. It lets a reader judge the position at a glance.

What is BRAG status, and why do some teams use it?

BRAG adds a fourth colour — Blue — to RAG, used for work that is complete (delivered and signed off). Teams add it because, under plain RAG, finished work stays Green and hides among the work still in progress; Blue separates “done” from “on track”, so the report shows the true amount of work still in flight and its real risk. A minority of teams use Blue for “ahead of plan” instead, so define it in a short key on the report.

How often should you send a project status report?

Weekly while a project is in active delivery or sitting at Amber or Red; fortnightly or monthly for steadier projects and for senior or board audiences. Whatever you choose, keep it regular — a report that arrives on the same day each week earns far more trust.

What is the difference between a status report and a project-on-a-page?

A status report is a regular written update with the detail behind each section. A project-on-a-page is an even shorter, often visual, one-page summary — usually for a board or senior audience who want only the headlines. The status report is the working document; the project-on-a-page is the digest.

Who writes the project status report?

Usually the project manager, drawing on updates from the team. The sponsor and stakeholders are the readers. On a very small project, the person doing the work writes it for whoever is paying for or overseeing the project.

This article is general guidance on project reporting, not formal project-management certification material or legal advice. Adapt the template to your organisation’s own governance requirements. Updated 14 June 2026.