Last updated: 31 May 2026
In short: a Project Initiation Document (PID) is the single document that defines why a project is happening, what it will deliver, how it will be run and who is accountable — agreed and signed off before delivery begins. In PRINCE2 it is the project’s contract and baseline: once approved, every later decision is measured against it. This guide explains what a PID is, walks through each section with examples, includes a worked example and a free Microsoft Word template, and shows how to get yours approved and keep it useful once the project is underway.
⬇ Download the free PID template for Microsoft Word
What is a Project Initiation Document (PID)?
A Project Initiation Document brings together, in one place, everything a sponsor and project board need in order to authorise a project and everything the team needs in order to run it. It captures the project’s background and business case, its objectives and scope, the deliverables, schedule, budget, risks, governance and the people involved.
The term comes from PRINCE2, the project management method widely used across UK government and industry, where the PID is a formal management product created at the end of the Initiating a Project stage. You do not have to run a PRINCE2 project to use one, though — a PID is good practice on any project of meaningful size, whether you follow PRINCE2, APM, or your own in-house method.
The most useful way to think about a PID is as a contract between the people paying for the project and the people delivering it, and as a baseline you can measure against. When someone asks “was that always in scope?” or “why are we doing this?”, the answer should be in the PID. It is a living document — it is updated through formal change control as the project evolves — but the version signed off at the start is the reference point everything else is judged against.
PID vs Project Charter vs Business Case vs Project Plan
These four are constantly confused. Here is how they differ and how they fit together.
| Document | What it is | When it’s created | Owned by |
|---|---|---|---|
| Business Case | The justification — why the project is worth doing, costs vs benefits. Feeds into the PID. | Before the project is approved | Sponsor / Senior Responsible Owner |
| Project Charter | A short, high-level document that authorises the project and appoints the project manager. Common in PMI/PMBOK practice. | At the very start, before the PID | Sponsor |
| Project Initiation Document (PID) | The detailed, definitive document that defines how the whole project will be delivered and controlled. Often absorbs the charter and business case. | End of initiation, before delivery | Project Manager (approved by the board) |
| Project Plan | The detailed schedule of tasks, dependencies, resources and dates. Sits underneath the PID. | After the PID is approved, and updated throughout | Project Manager |
In short: the business case says it is worth doing, the charter says you may start, the PID says exactly how it will run, and the plan is the day-to-day schedule that delivers it. On smaller projects the charter and business case are often folded into the PID itself.
Why a PID matters
A good PID is not box-ticking. It earns its place because it:
- Forces alignment before money is spent. Writing it surfaces the disagreements about scope and objectives that would otherwise appear halfway through delivery, when they are far more expensive to resolve.
- Defines “done”. Clear objectives and success criteria mean everyone knows what the project is committing to — and, just as importantly, what it is not.
- Controls scope creep. Because the PID is the baseline, any new request can be measured against it and put through change control rather than quietly absorbed.
- Provides governance and an audit trail. For projects spending capital or producing an asset, the PID is part of the evidence that the project was run to a professional standard.
- Onboards new people quickly. A team member joining in month four can read the PID and understand the whole project in twenty minutes.
What goes into a PID? The standard sections
There is no single legally mandated structure, but a complete PID — and the free template below — covers the following. Treat it as a checklist:
- Project information — name, sponsor, project manager, dates, document control
- Background and business case — why the project exists and the justification
- Objectives and success criteria — what success looks like, measurably
- Scope — what is in, and explicitly what is out
- Deliverables — the functional and non-functional outputs
- Schedule and key milestones — the high-level timeline
- Budget and financial information — capital and operational costs
- Risks — the initial risk register
- Key stakeholders — who needs to be engaged, and how
- Governance and controls — the project board, reporting, and decision-making
- Assumptions and constraints — what you’re taking as given, and your limits
- Version control / change log — how the document itself is managed
The PID template, section by section
Below we walk through each section of our free PID template, with a screenshot of the section and a note on what to put in it. Download the template and follow along.
Project information header
The cover details: project name, sponsor and project manager, key dates, and the document reference. Small but important — it tells anyone picking up the document what it is and how current it is.

Version control / change log
Because the PID is a living document, every published change is logged here with a date, version number, author and a short description of what changed. While Microsoft Word tracks changes automatically, a formal change log records the date of each version you circulate or have re-approved — which is what matters for governance.

Project financial information
Capture the budget: capital expenditure, operational costs, and any phasing across financial years. Be clear about what is estimated versus approved, and note who holds the budget.

Project objectives
State what the project will achieve in clear, measurable terms. Good objectives are specific enough that, at closure, you can demonstrate whether each was met. Tie them back to the benefits in the business case.

Project scope
The single most valuable section for preventing later argument. List what is in scope, and — just as importantly — what is explicitly out of scope. The “out of scope” list is your first line of defence against scope creep.

Project deliverables
The tangible outputs, split into functional deliverables (what the solution does) and non-functional deliverables (performance, security, compliance, documentation). Each should be specific enough to be acceptance-tested.

Schedule and key milestones
A high-level timeline — not the full project plan, but the major milestones and decision points the board will track. The detailed plan sits underneath the PID and is built once it’s approved.

Project risks
Your initial risk register: the significant risks known at the outset, their likely impact, and how you intend to respond. Once the project is running, the project manager maintains a standalone Risk Register reviewed at each board meeting.

Key stakeholders
Identify who has an interest in the project, their influence and what they need from it. This underpins your communications planning and your governance.

Governance and controls
How the project will be steered: the project board membership, the reporting cadence, tolerances, and how decisions and escalations are made. This is the section auditors and sponsors scrutinise most closely.

Worked example: a PID in practice
To make this concrete, here is an illustrative example for a typical UK project — replacing a 150-person company’s ageing HR and payroll system with a cloud-based platform. (This is a worked illustration, not a real client project.)
- Background / business case: the current HR system is unsupported from next year and cannot handle new statutory reporting. Replacing it avoids compliance risk and saves an estimated £40k a year in manual processing.
- Objective & success criteria: a new cloud HR/payroll platform live by 1 April, processing the first payroll run with zero errors and self-service adopted by 80% of staff within three months.
- In scope: core HR records, payroll, employee self-service, data migration. Out of scope: recruitment/ATS, learning management, and any process redesign beyond the new system’s standard workflows.
- Key deliverables: configured platform, migrated and validated data, integrations to finance, trained staff, and signed-off parallel payroll runs.
- Top risks: data quality in the legacy system (high); payroll cut-over timing around the tax year (high); user adoption (medium).
- Governance: monthly project board chaired by the Finance Director (sponsor), fortnightly delivery checkpoints, change requests over £5k or affecting the go-live date escalated to the board.
Notice how much potential conflict that single “out of scope” line removes — and how the success criteria turn a vague “new HR system” into something you can actually prove you delivered.
How to create your PID in seven steps
- Start from the template and the business case — don’t begin with a blank page.
- Draft the background, objectives and scope first. Everything else flows from these. Get them right before adding detail.
- Work with your stakeholders, not in isolation. Use a shared Word or Google Docs file so the sponsor, finance and key stakeholders can comment. The act of agreeing the PID is the alignment.
- Fill in deliverables, schedule and budget at the level of detail appropriate to the stage — enough to commit to, not so much that it’s guesswork dressed as fact.
- Add the initial risk register and governance. Be honest about risks; a PID with no real risks signals it hasn’t been thought through.
- Review against the checklist above and have the project board formally approve it.
- Baseline it. Save the approved version, set the version number, and treat every later change as a controlled change.
Getting your PID approved: the governance bit
A PID has no force until it is signed off. Approval usually flows from the project manager, who prepares it, to the sponsor (or Senior Responsible Owner) and the project board, who authorise it. Build approval time into your initiation schedule — it is the step most often left to the last minute.
If approval stalls — a key approver is unavailable, or finance won’t commit the budget — escalate early rather than starting delivery on an unapproved document. Starting work against a PID that hasn’t been signed off is one of the most common ways projects lose their governance footing.
Keeping your PID alive: when to update it
“Living document” is easy to say and easy to ignore. In practice, update and re-baseline the PID when:
- The scope, budget or timeline changes materially (through change control, with board approval)
- The sponsor, project manager or governance arrangements change
- A major new risk emerges that changes the project’s shape
- At each major stage boundary, as a scheduled review
Each update goes in the version-control log. Day-to-day progress lives in your reports and plan, not in the PID — reserve PID changes for things that move the baseline.
Using your PID to stop scope creep
The approved PID is your most effective tool against scope creep. When a new request arrives mid-project, the test is simple: is it in the approved scope? If yes, deliver it. If no, it goes through change control — assessed for impact on time, cost and risk, and approved (or declined) by the board. The PID lets you say “happy to do that — here’s the change request” instead of either refusing outright or quietly absorbing extra work that blows the budget. Point back to the “out of scope” list and the change log, and the conversation stays professional and evidence-based.
Download the free PID template
⬇ Download our free Project Initiation Document template (Microsoft Word)
The template suits both software and non-software projects — delete the sections you don’t need.
These templates are free to use for your own projects but may not be resold. For where to store your PID and the rest of your project documents, see our project management folder structure template.
Frequently asked questions
What is a Project Initiation Document (PID)?
A PID is the document that defines a project’s background, objectives, scope, deliverables, schedule, budget, risks and governance, agreed and signed off before delivery begins. It acts as the project’s contract and baseline.
What should a PID include?
Project information, background and business case, objectives and success criteria, scope (in and out), deliverables, schedule and milestones, budget, risks, key stakeholders, governance and controls, assumptions and constraints, and a version-control log.
What is the difference between a PID and a project charter?
A project charter is a short document that authorises the project and appoints the project manager. A PID is more detailed and comes next, defining exactly how the project will be delivered and controlled. On smaller projects the charter is often folded into the PID.
Who writes the PID and who approves it?
The project manager prepares the PID, working with stakeholders. It is approved by the sponsor (or Senior Responsible Owner) and the project board before delivery starts.
Is a PID a PRINCE2 document?
The term comes from PRINCE2, where the PID is a formal management product. But the concept is useful on any project, regardless of the method you follow.
What is the difference between a PID and a project plan?
The PID defines the whole project — why, what, how and who. The project plan is the detailed schedule of tasks, dependencies and dates that sits underneath it and is updated throughout delivery.
Recommended reading: PRINCE2 and project initiation books
A project initiation document is a PRINCE2 product, so the best reading starts there. These titles explain what belongs in a PID, how it is approved, and how to scope and define a project well at the outset. Every link goes to Amazon UK.

PRINCE2 7: Managing Successful Projects
PeopleCert
The PID is a PRINCE2 product. The official manual defines exactly what the document should contain and how it is approved.
View on Amazon
PRINCE2 Study Guide: Update for PRINCE2 7
David Hinde
A clear, exam-focused walkthrough of PRINCE2 7, with worked examples that explain the PID and its components in plain English.
View on Amazon
Project Management for the Unofficial Project Manager
Kory Kogon & Suzette Blakemore
Writing your first initiation document without formal training? This covers planning and scoping a project from scratch.
View on Amazon
Mike Clayton
Strong on defining a project properly at the outset — the thinking that goes into a good PID, project brief and business case.
View on AmazonDisclosure: as an Amazon Associate, IT Management 101 earns from qualifying purchases. We may receive a small commission if you buy through the links on this page, at no extra cost to you. Availability and prices are set by Amazon and can change.
