A project charter is a short document — usually one to three pages — that authorises a project, names who is in charge, and sets out what it will and will not deliver. It is signed off by the person paying for the work (the sponsor) before any real spending starts. You can download a free, editable UK template in Word and Excel below, with a worked example filled in. No email address required.
Key takeaways
- A charter answers four questions: why are we doing this, what will it deliver, who is responsible, and by when and for how much.
- The five elements every charter needs: purpose, objectives, scope, key stakeholders, and high-level risks. A fuller charter adds milestones, budget, and success criteria — seven in all.
- In the UK, “project charter” is the American (PMI) term. PRINCE2 and most public-sector bodies split the same job across a Project Brief and a Project Initiation Document (PID). We map them below.
- Keep it to one to three pages. If it is sprawling, you are writing a plan or a business case, not a charter.
- Download the free Word and Excel template below — blank, plus a filled UK small-business example.
What is a project charter?
A project charter is a brief, formal document that gives a project the go-ahead. It records the project’s purpose, its goals, its boundaries, the people accountable for it, and the headline budget and timeline. Its real job is authority: it is the point at which a sponsor — the senior person funding the work — says “yes, start”, and grants the project manager permission to use the organisation’s time and money.
Think of it as the project’s terms of reference. It is written at the very start, before detailed planning, and it stays short on purpose. A good charter can be read in five minutes and pinned to the wall. Everything in it is a heading the detailed plan will later expand.
A note on jargon: the sponsor is the budget holder who owns the project’s success. The scope is the agreed boundary of what is included. A stakeholder is anyone affected by, or able to affect, the project. We define the rest as we go.
Where a charter sits: the UK governance map
This is the part most guides skip, and it matters if you work in the UK. The term “project charter” comes from the American Project Management Institute (PMI). British organisations — and almost all of the public sector, the NHS, and central government — tend to use PRINCE2 (PRojects IN Controlled Environments, version 2), which does the same job under different names. If someone asks you for a “PID” or a “project brief”, they are asking for the charter’s close cousins.
So: a project charter (the PMI term) authorises the project and sets its direction in one document. PRINCE2 splits that work — a project brief sets the early direction, but formal authorisation to proceed comes a step later, when the project board approves the PID (Project Initiation Document), the heftier document that adds the detailed controls. So the charter is closest to the brief in role, while the PID is where a PRINCE2 project is formally signed off. A business case sits before all of them and answers a different question: is this worth doing at all? Here is how they compare.
| Document | Question it answers | Length | UK equivalent |
|---|---|---|---|
| Business case | Is it worth doing? Do the benefits beat the cost? | 2–20 pages | Same term |
| Project charter | Are we authorised to start, and what is the direction? | 1–3 pages | Project Brief (PRINCE2) |
| PID | How exactly will we control and govern it? | 10–40 pages | PRINCE2 native |
| Project plan | Who does what, in what order, by when? | Schedule/Gantt | Same term |
The practical rule: if you are in a PRINCE2 or public-sector setting and someone asks for a charter, give them a Project Brief; the two are interchangeable for most purposes. If they ask for a PID, they want considerably more detail than a charter holds.
The 7 elements of a project charter
Ask “what are the five elements of a project charter?” and the honest answer is: purpose, objectives, scope, key stakeholders, and high-level risks. Different sources count the elements differently — PMI’s own component list runs longer — but those five are the practical core. A charter that earns its keep adds two more — milestones and budget, and clear success criteria — giving seven. Here is what each one holds.
- Purpose and business need. One or two sentences on why the project exists and the problem it solves. This is the charter’s anchor; every later decision is tested against it.
- Objectives and deliverables. What the project will produce, stated so you could tick each one off. “A live e-commerce site taking card payments” beats “improve our online presence”.
- Scope — in and out. The boundary. Crucially, list what is out of scope as well as in; an explicit “not included” line prevents most scope creep.
- Key stakeholders and roles. The sponsor, the project manager, and the handful of people who must be involved or kept informed. Name them; do not write “the marketing team”.
- High-level risks and assumptions. The three or four things most likely to derail the project, and the assumptions you are relying on (for example, “the supplier can deliver by August”).
- Milestones, timeline and budget. The headline dates and the money. Not a detailed schedule — that comes later — but the start, the key checkpoints, the end, and the budget envelope.
- Success criteria and sign-off. How you will know it worked, and the sponsor’s signature and date. The signature is the whole point: it is the authorisation.
A filled example: a UK small business
Most charter examples online describe a US construction firm or a marketing campaign at a large agency. Here is a complete one for a real UK situation: a small homeware shop, Wren & Willow (an illustrative example, not a real firm), replacing its tired website with a proper online shop. The figures are realistic for a business of that size.
| Project | Wren & Willow online shop relaunch |
| Purpose | Our current site cannot take payments; customers phone or visit. Build a shop that sells online to lift revenue beyond the shop’s opening hours and catchment. |
| Objectives | A live shop on our domain taking card and Apple Pay; 150 products listed; click-and-collect; integrated with our till’s stock count. |
| In scope | Website build, payment setup, product photography, staff training, launch. |
| Out of scope | A mobile app; international shipping; a loyalty scheme (phase two). |
| Stakeholders | Sponsor: Anna (owner). Project manager: Ravi (operations). Web agency: external. Staff: two part-time, for training. |
| Risks & assumptions | Risk: product photography slips the launch. Risk: stock-sync with the till proves fiddly. Assumption: the agency starts in July as quoted. |
| Timeline | Start July 2026 · build Aug · soft launch 15 Sept · full launch 1 Oct 2026. |
| Budget | £6,500 build and setup; £90 per month running; £400 photography. Contingency £1,000. |
| Success criteria | Live by 1 Oct; 20 online orders in the first fortnight; stock count stays accurate to within five items. |
| Sign-off | Anna (Sponsor) — signature and date. |
Notice how little it says, and how much it settles. Everyone now knows the project ends on 1 October, costs about £8,000 to set up plus about £90 a month to run, does not include an app, and is judged on twenty orders in a fortnight. That is a charter doing its job.
Do you even need a charter? A two-minute decision
Not every piece of work needs a formal charter. For a cost-conscious founder or a small team, the honest question is how much governance the project actually warrants. Use this.
The rule of thumb: if a project will spend real money, run for more than a few weeks, or involve people who do not sit next to you, write a charter. If it is small and quick, a few lines in an email carry the same authority with less ceremony. And if you are in a regulated or public-sector environment, expect to go further, to a full PID.
How to write a project charter, step by step
- Draft the purpose first. If you cannot write the “why” in two sentences, the project is not ready to charter.
- List deliverables, then draw the boundary. Write what is in scope, then deliberately write what is out — the exclusions do most of the work.
- Name people, not teams. Put a real name against sponsor and project manager. Ambiguous ownership is the most common reason charters fail to prevent drift.
- Add the headline dates and budget. Keep it to milestones and an envelope. Detail belongs in the plan.
- Write the success criteria as tests. Each one should be something you can later mark pass or fail.
- Get the sponsor to sign. An unsigned charter is a draft. The signature is the authorisation, and the moment to raise any disagreement is before it is given.
Treat the charter as a living document in only one sense: if the project’s purpose, budget or scope genuinely changes, revise the charter and have the sponsor re-sign. Day-to-day changes belong in the plan and the change log, not here.
Who writes it, who approves it, and how long it should be
Who writes it: usually the project manager, often with the sponsor. Who approves it: the sponsor signs; in a larger organisation a steering group or project board may also approve. How long: one page for a small project, two to three for a larger one. If your charter runs past three pages, you are probably writing a PID or a plan, and should split it.
What to leave out: a detailed task schedule, a full risk register, technical specifications, and a line-by-line budget. Those are real documents — they are not the charter. Keeping them out is what keeps the charter readable, and a readable charter is one people actually use.
Download the free UK project charter template
Free, editable, no email required. Each file includes a blank charter and the filled Wren & Willow example above, so you can see exactly how it is used.
- Word template (.docx) — the one-page charter, ready to type into. Download Word version
- Excel template (.xlsx) — the same fields with a structured layout and a sign-off row. Download Excel version
UK English, A4, designed for small businesses. Made by a practitioner, not a software vendor — there is nothing to sign up for.
If you also need the documents that sit either side of the charter, our Project Initiation Document (PID) template covers the fuller PRINCE2 version, and the project-on-a-page template is a good one-page status summary once the project is running. The project folder structure template gives them all a tidy home.
Frequently asked questions
What are the five elements of a project charter?
Purpose, objectives, scope, key stakeholders, and high-level risks. These five are the core. A fuller charter adds milestones and budget, and success criteria, making seven.
What is the difference between a project charter and a PID?
A charter authorises the project and sets its direction in one to three pages. A PID (Project Initiation Document) is the more detailed PRINCE2 document that follows, adding the controls — governance, risk management, quality and reporting — over ten to forty pages. In simple terms, the charter says “go and here is the direction”; the PID says “and here is exactly how we will run it”.
Is a project charter the same as a project brief?
For most purposes, yes. “Project charter” is the PMI (American) term; “project brief” is the PRINCE2 (British) term for the document that authorises a project and sets its direction. If a UK or public-sector colleague asks for a brief, a charter will satisfy them.
Is a project charter the same as a project plan?
No. The charter sets the direction and authorises the project in one to three pages; the project plan works out the detail — the tasks, the order, the schedule and who does what. The charter comes first and stays short; the plan comes after and grows as the project does.
Who writes and approves a project charter?
The project manager usually writes it, often with the sponsor. The sponsor approves and signs it; in larger organisations a steering group or project board may also sign off. The signature is what grants the project manager authority to proceed.
How long should a project charter be?
One page for a small project, two to three for a larger one. If it runs longer, you are writing a plan or a PID, not a charter.
What should not be in a project charter?
A detailed task schedule, a full risk register, technical specifications, and a line-by-line budget. Those belong in the plan, the risk register and the budget document. Keeping them out is what keeps the charter short enough to be useful.
This article is general guidance on project documentation, not formal project-management certification material or legal advice. Adapt the template to your organisation’s own governance requirements. Updated 14 June 2026.