Change Request Form Template — Free Word & Excel

A change request form is a one-page document that records a proposed change to a project — what is being asked for, why, what it would affect, and who approved or rejected it. It turns “can we just add this?” into a decision someone owns. Below are two free UK templates — a Word form and an Excel change log — with a worked example and a short guide to using them. CR stands for change request.

Download the free change request templates

A ready-to-use UK change request form (Word) and a change log to track every request to a decision (Excel). Both with a worked example. Free, editable, no sign-up and no email.

UK format · Microsoft Word and Excel · instant download · written by a practitioner, not a software vendor.

The short version

• A change request form captures one proposed change: description, reason, options, impact and decision.

• The point is to assess a change before you make it — on scope, time, cost, quality and risk.

• A change log (or change register) lists every request so none is lost or quietly actioned.

• Even a two-person project benefits, because it stops scope creep — small additions that pile up unnoticed.

• The free Word form and Excel log below give you both, with a worked example to copy.

What a change request is (and why it matters)

A change request is a formal note that something about a project should be different from the plan — a new feature, a dropped requirement, a revised deadline, a swapped supplier. Change control is the simple discipline of writing each one down, weighing it up, and deciding on it deliberately rather than on the spot. The form is the artefact; change control is the habit.

The reason this matters has a name: scope creep. Scope creep is the slow expansion of a project through a run of small, individually reasonable additions, none of which felt big enough to question at the time. “While you are at it, could you also…” is how budgets quietly overrun and deadlines quietly slip. A change request form is the speed bump. It does not say no to changes; it makes each one visible, costed and owned before it happens.

This is true whether you run a thirty-person programme or a two-person job. The thirty-person programme has a RAID log and a board. The two-person job has a shared spreadsheet and a quick conversation. The mechanism is the same: a change is requested, its impact is assessed, someone decides, and the decision is recorded.

Want the full set? The Change Control Pack

The free form and log above cover most small projects. If you run change formally — or want the complete kit — the Change Control Pack adds a change control board (CCB) terms-of-reference, an impact-assessment scoring sheet, an approval-workflow one-pager, and a combined change register with charts. £19, one-off.

See what is in the pack

Do small teams really need formal change control?

Honestly, not always — and pretending otherwise wastes your time. The right amount of process depends on the size of the project and the cost of getting a change wrong. Here is the ladder, cheapest first.

  • A tiny, one-person job. A change is a thought you have and act on. Writing a form would take longer than the change. Skip it — keep a one-line note of anything you spent money on, and move on.
  • A small project with someone paying. This is where a change log earns its keep. The moment money or a deadline is involved, a one-line entry per change stops awkward “but I never agreed to that” conversations. Use the free Excel log below.
  • A project with several people or a fixed budget. Add the Word form, so each significant change gets its impact assessed and a recorded decision before it goes ahead.
  • Formal or regulated work. Add a change control board (CCB) — the small group that approves changes — and a documented workflow. That is where the £19 pack helps.

The free templates here cover the middle two rungs, which is where most small businesses actually sit. Start there and add formality only when a change going wrong would genuinely hurt.

What goes in a change request form

A good change request form is short and predictable. It opens with a document-control block — the housekeeping that keeps the right version in circulation — then walks through the change from description to decision. These are the fields in the free template.

FieldWhat it captures
CR numberA unique reference (CR-001, CR-002…) so you can refer to the change later and find it in the log.
ProjectWhich project or workstream the change belongs to.
Raised by & dateWho is asking, and when. Useful when you come back to it weeks later.
DescriptionExactly what is being asked for. Specific beats vague: name the affected deliverable.
Reason / justificationWhy the change is needed, and what happens if it is not made. This is the business case in miniature.
ImpactThe effect on scope, time, cost, quality and risk — the five things every change touches. Covered in its own section below.
PriorityLow, medium or high — how urgent the change is relative to everything else.
Options consideredThe alternatives the team looked at, including doing nothing. Decisions read better when the road not taken is on record.
RecommendationWhich option you recommend, and why.
DecisionApprove, reject or defer — plus who decided and when.
Implementation notesHow an approved change will be carried out: dependencies, sequencing, and a rollback plan if it needs undoing.

The impact assessment: the five things every change touches

The heart of the form is the impact assessment. Any change pushes on five levers, and a good request says something about each — even if the answer is “no effect”.

AreaThe question to answer
ScopeDoes it add, remove or change what the project delivers?
TimeDoes it move a milestone or the end date?
CostWhat does it cost, in money and in effort?
QualityDoes it affect quality, testing or what counts as “done”?
RiskDoes it introduce a new risk, or change an existing one?

Scope, time and cost are the classic three constraints — move one and you usually move another. Adding quality and risk to the assessment is what turns a wish into a properly weighed decision.

How to fill in the form and use the log

The two templates work together: one form per change to think it through, one row per change in the log to keep track. This is the change control process in miniature — raise, assess, decide, implement — and here is the routine step by step.

  1. Open a form for the change. Give it the next CR number, name the project, and note who is raising it and when.
  2. Describe the change and the reason. Say what is being asked for, specifically, and why — including what happens if it is not done.
  3. Assess the impact. Work through scope, time, cost, quality and risk. Put a number on the cost and the time where you can; an estimate beats a shrug.
  4. List the options and recommend one. Include doing nothing. Say which option you recommend and why.
  5. Take a decision. Approve, reject or defer it — and record who decided and when. A deferred change is a real outcome, not a non-answer.
  6. Log it. Add a row to the Excel change log: CR number, date, title, impact, priority and status. The log is your at-a-glance view of every request.
  7. Implement and close. If approved, follow the implementation notes, then set the status to Implemented in the log. The summary counts update as you go.
1. Raisefill in the form2. Assessscope, time, cost,quality, risk3. Decideapprove / reject /defer4. Implementand log itrejected or deferred → record in the log and stop
The change control workflow: raise, assess, decide, implement — with rejected and deferred changes recorded too.

Start from the templates

Prefer not to begin with a blank page? The free Word form contains the worked example below and a blank to copy. The Excel log has dropdowns for status and priority, colour-coded statuses, and a live count that updates as you type.

A worked example

To make the form concrete, here is a completed one. Harbour & Vine is an illustrative cafe fit-out. Mid-project, the owner asks for outdoor seating — exactly the sort of “while we are at it” addition that change control exists to handle.

CR-014 — Harbour & Vine cafe fit-out

• Raised by: Priya Shah (operations), 10 Jun 2026. Priority: high.

• Change: add an outdoor seating area for eight covers on the side terrace, with weatherproof furniture and a retractable awning.

• Reason: weekend bookings outrun indoor capacity and customers are turned away; the terrace is unused. Extra covers should recover the cost within one trading season.

• Options: do nothing (lose trade); a fixed pergola (dearer, planning query); a retractable awning plus movable furniture (cheaper, no planning issue) — recommended.

• Impact: scope +8 covers; time two days within an existing closure; cost about £2,600; quality unchanged indoors; risk weather-dependent, mitigated by the awning.

• Decision: approved by Tom Reilly (owner), 12 Jun 2026.

Notice what the form forced into the open: a costed figure, a checked floor load, a rejected alternative, and a named approver with a date. Six weeks later, when someone asks why there is an awning on the terrace, the answer is one row in the log away. Both the blank and this filled example are in the downloads.

The approval workflow and the change control board

Who decides? On a small job, the person paying. On a larger one, a change control board (CCB) — a small standing group, often the project sponsor, the project manager and someone who understands the budget, who meet (or exchange messages) to approve, reject or defer changes. The CCB is not bureaucracy for its own sake; it is a named place where the decision lands, so it does not get made twice or not at all.

Every decision has three honest outcomes, and a good workflow uses all three.

DecisionWhat it meansWhat happens next
ApproveThe change goes ahead as recommended.Implement it; update the plan and the log; mark it Implemented when done.
RejectThe change will not be made.Record the reason in the log. A documented “no” stops the same request coming back.
DeferNot now — revisit later.Park it with a date or trigger to review. Deferring is a decision, not a dodge.

If you keep a decision log as well, the approval is a natural entry there too. The change request form explains the reasoning; the decision log and the change log are where the outcome is recorded so it is not forgotten.

Using the Excel change log

The form is for one change at a time. The change log — sometimes called a change register — is the running list of all of them. It is the page you glance at to answer “what is outstanding, and what did we decide?”

The free Excel log has a column for each thing worth tracking — CR number, date raised, title, who raised it, the impact, priority, status, decision date, owner and notes. Three details make it genuinely useful rather than a bare grid:

  • Dropdowns for status (Open, Approved, Rejected, Implemented) and priority (Low, Medium, High), so entries stay consistent.
  • Colour-coded statuses — amber for Open, green for Approved, red for Rejected, blue for Implemented — so the state of play is visible at a glance.
  • A live summary that counts how many requests sit at each status and updates the moment you change one. No manual tallying.

Both the Word form and the Excel log come with a worked example tab built from the Harbour & Vine project, so you can see them in use before you start your own.

Where this fits with your other project documents

A change request form does not work alone. It sits alongside the other small documents that keep a project honest, and the free templates here are part of a set.

  • A RAID log tracks risks, assumptions, issues and dependencies; a big change often starts life as a risk or an issue there.
  • A decision log records the reasoning behind significant choices, including change approvals.
  • A risk register is where new risks raised by a change belong.
  • A project status report is where you flag, each period, the changes that were approved and what they did to the plan.

For the bigger picture of why changes need managing at all — the people side, not just the paperwork — see our piece on the art of change management.

Frequently asked questions

What is a change request form?

A change request form is a one-page document that records a proposed change to a project: what is being asked for, why, the impact on scope, time, cost, quality and risk, the options considered, and the decision to approve, reject or defer it. It makes each change a deliberate, owned decision rather than an on-the-spot “yes”.

What should a change request form include?

At minimum: a unique CR number, the project, who raised it and when, a description, the reason or business justification, an impact assessment, the options considered, a recommendation, and the decision with the approver and date. Implementation notes and a priority are useful additions. The free template lays out exactly these fields.

What is the difference between a change request and a change log?

A change request (and its form) is about one proposed change — the full detail of that single item. A change log, or change register, is the running list of all change requests, one row each, showing their status and decision. You use the form to think a change through, and the log to keep track of every change across the project.

Who approves a change request?

On a small project, whoever is paying or running the work. On a larger one, a change control board (CCB) — a small group, typically the project sponsor, the project manager and someone across the budget, who decide to approve, reject or defer each request. The key is that approval lands in one named place and is recorded.

Do small projects need a change request form?

Not every one. A tiny, one-person job rarely justifies a form — a one-line note is enough. But the moment money or a deadline is involved, even a lightweight change log pays for itself by stopping scope creep and “I never agreed to that” disputes. The honest rule of thumb is: add formality only when a change going wrong would genuinely hurt.

What is scope creep, and how does a change request form stop it?

Scope creep is the gradual expansion of a project through a series of small additions, none of which seemed big enough to question at the time, that together blow the budget or the deadline. A change request form stops it by making every addition visible and costed before it happens — so the cumulative effect is seen, and someone owns the choice to take it on.

What is a change control board (CCB)?

A change control board is the small group responsible for approving, rejecting or deferring change requests on a project. It usually includes the project sponsor, the project manager and someone who understands the budget. On a small project the “board” might be one person; the point is that there is a clear, named place where change decisions are made and recorded.

Written by Linda Garrould for IT Management 101. Updated 15 June 2026. The Harbour & Vine example is illustrative. The Word and Excel templates are free to use and adapt, with no attribution required. General guidance for UK small businesses, not formal project-management certification material.